Motorists will experience new traffic configurations along the construction zone on State Road 37 and 141st Street. Traffic is being diverted to the west side of the project. There are several other ongoing and updates construction zones in and around Fishers.
Here is the latest Fishers area road construction report provided by the City of Fishers, for the work week starting Monday, May 19:
UTILITY WORK- LANE RESTRICTIONS
Beginning the week of May 12, the contractor will be running fiber on Southeastern Pkwy between Atlantic Road and Cyntheanne Road, drivers should expect intermittent lane restrictions between 9am to 3pm.
STATE ROAD 37 IMPROVEMENT PROJECT
State Road 37 and 141st Street
Traffic Switch – Complete
The eastside of 141st St. at SR37 is currently closed for the next phase of construction. Traffic has transitioned to the westside, with SR37 north and southbound lanes remaining open. Please review detour routes to plan ahead during this time. Thank you for your continued patience and remember to drive cautiously and safely through construction areas. All construction updates will be posted to DriveFishers on X(Twitter) and 37Thrives on Facebook. Please visit 37thrives.com to sign-up for email updates. See the detour route here and the business detour route here.
To learn more about the State Road 37 Improvement Project and sign up to receive text updates, visit 37Thrives.com.
CLEAR PATH IMPROVEMENT PROJECT
To learn more about the Clear Path Improvement Project and sign up to receive text and email updates, visit clearpath465.com
I-465 & I-69
Drivers will see an increase in construction along the I-69 corridor in the coming months. This work will focus on reconfiguring the interchange at I-465 and I-69. New ramps will provide direct movements from eastbound I-465 and northbound I-465 to northbound I-69. Binford Blvd. will also be reconstructed to separate local traffic from traffic entering and exiting I-69 and I-465. Access to I-69 from Binford Blvd. will remain open.
Short-Term Closures
Friday, May 16 (11p.m. to 6 a.m.)
- Ramp from southbound I-69 to Binford Boulevard closed
- Ramp from southbound I-69 to southbound I-465 alternating lane closures
- Ramp from southbound I-69 to southbound I-465 rolling closures (starting at midnight)
Long-Term Closures
- Ramp from 56th Street to I-465
- Ramp from Allisonville Road to I-465 eastbound
- Ramp from northbound Binford Boulevard to I-465 westbound
82nd Street Ramps
For detour routes and additional project information, visit clearpath465.com.
For additional project information, visit the 146th Street & Allisonville Rd. Project Page.
121ST STREET AND HOOSIER ROAD – FUTURE ROUNDABOUT
There will be a full closure in place at 121st and Hoosier Road for the construction of a roundabout beginning on or after May 29 – this will be a 60 day closure. The detour route is 126th Street, Cumberland Road, 116th Street, see map here.
131ST STREET AND HOWE ROAD – FUTURE ROUNDABOUT
There will be a full closure in place at 131st and Howe for the construction of a roundabout beginning on or after May 29 – this will be a 60 day closure. The detour route is Cumberland Road, 141st street, and Promise Road, see map here.
136TH STREET WIDENING – ROAD CLOSURE
As of Tuesday, April 1, 136th Street between Prairie Baptist Road and Cyntheanne Road has been closed to through traffic as construction begins on the reconstruction of the roadway. Access to all of the homes and fire station off of 136th Street will be maintained only to eastbound traffic. Westbound traffic will need to follow the attached detour route. Access into Hunters Run and Silverton will be off of Prairie Baptist or Cyntheanne Road. See a map of this closure here.
In addition, there will be a 10 day closure on 136th Street from Prairie Baptist Road to Fire Station #97.
SOUTHEASTERN PARKWAY RESTRICTIONS
Beginning on or after April 21st, expect to see lane restrictions along Southeastern Parkway, Cyntheanne Road and 126th Street as utilities perform aerial work along the roadway. Flaggers will be in place between 9AM and 3PM.
PROJECTS SOUTH OF 116TH STREET
96TH STREET LANE RESTRICTIONS
Beginning May 15 there will be lane restrictions in place between Hague Road to Masters Road on 96th Street. These will take place between 9am to 3pm and will be ongoing for 3 weeks.
The 96th & Allisonville roundabout is now open and accessible in all directions, making travel smoother and safer at one of the main gateways to our City. Please proceed with caution as this is still an active construction site. Expect periodic lane restrictions.
2025 ROAD RESURFACING PROJECT
As of Monday, May 5th our contractor has begun curb and curb ramp work in the Sawgrass Subdivision. Homeowners will be notified via door hangers prior to any curb reconstruction near their home. After ADA ramp and curb reconstruction is completed, those areas will be restored with topsoil and seed. It is the responsibility of the homeowner to water the seed for the seed to germinate. Prior to road resurfacing, residents will be notified via street signage for street parking restrictions. For additional project information, view the Capital Project Dashboard here.
View the Road Resurface Overview Map here.
The City of Fishers has partnered with the City of Carmel, Clay Township, Carmel Clay Parks and Recreation, Hamilton County, and Delaware Township to connect Heritage Park at White River and Carmel’s Hazel Landing Park with a bridge over White River. This new amenity will provide enhanced connectivity between the two communities, as well as new recreational opportunities for our residents. Click here for an aerial view. Construction is expected to occur Monday through Saturday beginning at 7 a.m. The bridge is expected to be complete in August 2025.