The summer construction season continues to be a busy one. There are changes coming to the Clear Path project at I-69 & I-465. Also, the Woofstock 5K is coming up August 9….be aware the the closures tied to that event.
There is a lot to review, so here is the weekly road construction report for the work week starting Monday, August 4, as provided by the City of Fishers:
Attention, Fishers! The annual Woofstock 5K race is happening soon, and we want to keep you informed about the road closures:
Event Date: 8/9/2025
Start Time: 8AM
End Time: Appox. 9:30AM
Road Closures:
🔹 Lantern Rd: Closed in both directions north and southbound from 126th Street to Commercial Drive during the 5K
🔹 Officers will allow traffic to exit from Trophy Drive & Wolford Drive on 126th westbound as deemed safe to do so in between runners.
🔹 Eastbound 126th St: Closed from Saksons Blvd to Lantern Rd. Westbound 126th will remain open.
🔹 Sunblest Neighborhood: Single Lane closures only along Sunblest Blvd, Ellipse Pkway, and Saksons Blvd
🔹 Traffic from Kenetta Ct, Kemble Ct, Bentley Blvd, and Farley Dr will be allowed to travel along Ellipse Pkway as deemed safe to proceed in between runners.
🔹 Traffic from the west side of Sunblest Blvd and Holland Dr will be closed.
🔹 Municipal Drive at Lantern Road will be closed.
See route map here. Please plan your travels accordingly and thank you for your cooperation. For more information, view the event page here.
State Road 37 and 141st Street
The eastside of 141st St. at SR37 is currently closed for the next phase of construction. Traffic has transitioned to the westside, with SR37 north and southbound lanes remaining open. Please review detour routes to plan ahead during this time. Thank you for your continued patience and remember to drive cautiously and safely through construction areas. All construction updates will be posted to DriveFishers on X(Twitter) and 37Thrives on Facebook. Please visit 37thrives.com to sign-up for email updates. See the detour route here and the business detour route here.
To learn more about the State Road 37 Improvement Project and sign up to receive text updates, visit 37Thrives.com.
Anticipated Completion: Summer of 2026
To learn more about the Clear Path Improvement Project and sign up to receive text and email updates, visit clearpath465.com
I-465 & I-69
Drivers will see an increase in construction along the I-69 corridor in the coming months. This work will focus on reconfiguring the interchange at I-465 and I-69. New ramps will provide direct movements from eastbound I-465 and northbound I-465 to northbound I-69. Binford Blvd. will also be reconstructed to separate local traffic from traffic entering and exiting I-69 and I-465. Access to I-69 from Binford Blvd. will remain open.
The eastbound I-465 ramp to Binford Boulevard is scheduled to close for up to 60 days beginning next Friday night, July 11, as part of the Clear Path 465 project on the northeast side of Indianapolis. The closure will allow crews to reconstruct the ramp. In addition, lane and ramp closures are scheduled for the weekend of July 11 at the I-465/I-69 interchange for crews to restripe pavement and move concrete barrier wall on Binford Boulevard.
The following closures are scheduled:
60 day closure starting Friday, July 11 at 9 p.m.
- Eastbound I-465 ramp to southbound Binford Boulevard closed
Safe Zones enforcement remains active in the Clear Path construction zone. The program uses automated systems to monitor speeds in specified work zones. The goal of the program is to keep workers, drivers, and their passengers safe by reducing excessive speeding and crashes in work zones. It’s important to slow down in construction zones and drive without distractions. Learn more about Safe Zones atSafeZonesIN.com
For schedule updates, follow the project onFacebook,XandInstagram, and subscribe to email and text message alerts at ClearPath465.com.
Short-Term Closures
Overnight Thursday, July 31 and Friday, August 1 (9 p.m. to 6 a.m. each night)
- Eastbound I-465 ramp to northbound I-69 closed
- Southbound I-69 ramp to southbound Binford Boulevard closed
- Northbound Binford Boulevard closed north of 75th Street
- No access to northbound/southbound Binford Boulevard from 75th Street
- No access to northbound I-69 from 75th Street
Overnight Monday, August 4 through Thursday, August 7 (9 p.m. to 6 a.m. each night)
- Southbound I-69 ramp to southbound I-465 closed
- 82nd Street ramp to southbound I-465 closed
- Eastbound/southbound I-465 right lane closed from main interchange to 56th Street
Overnight Friday, August 8 (9 p.m. to 6 a.m.)
- Northbound Binford Boulevard single lane closed north of 75th Street
Actual dates and anticipated work may be adjusted if inclement weather or other unforeseen circumstances occur. Drivers are encouraged to plan alternate routes and allow extra travel time during overnight hours.
Long-Term Closures
- Ramp from 56th Street to I-465 northbound
- Ramp from Allisonville Road to I-465 eastbound
- Ramp from northbound Binford Boulevard to I-465 westbound
82nd Street Ramps
For detour routes and additional project information, visit clearpath465.com.
|
BRIGHTSPEED FIBER INSTALLATION
Brightspeed will be installing fiber throughout the following areas: South Avalon Estates, Knoll at Thorpe Creek, Overlook at Thorpe Creek, Woods at Thorpe Creek, and Geist Overlook this week. Work will be conducted in the utility easement behind the sidewalk. |
|||||
|
PROJECTS NORTH OF 116TH STREET
146TH STREET & ALLISONVILLE ROAD – HAMILTON COUNTY PROJECT
Hamilton County, Indiana – Please be advised, beginning on or after Wednesday, July 23,2025, between the hours of 9AM to 3PM, drivers should expect intermittent ramp closures and additional traffic restrictions around the roundabout for asphalt paving and concrete curb construction. The intermittent closures and restrictions are expected to occur daily through August 15, 2025. Additional information identifying movement restrictions will be provided in future press releases as daily work plans are formalized. Please use extreme caution and follow the posted work zone speed limit while driving through this construction zone. Anticipated Completion Date: FALL 2025 For additional project information, visit the 146th Street & Allisonville Rd. Project Page. 121ST STREET AND HOOSIER ROAD – FUTURE ROUNDABOUTAs of May 29 a full closure has been in place at 121st and Hoosier Road for the construction of a roundabout, this will be a 60 day closure. Substantial Completion: The week of August 4, weather dependant. The detour route is 126th Street, Cumberland Road, 116th Street, see map here. 131ST STREET AND HOWE ROAD – FUTURE ROUNDABOUTAs of May 29 a full closure has been in place at 131st and Howe for the construction of a roundabout, this will be a 60 day closure. Substantial Completion: The week of August 11, weather dependant. The detour route is Cumberland Road, 141st Street, and Promise Road, see map here. 136TH STREET WIDENING – ROAD CLOSUREAs of Tuesday, April 1, 136th Street between Prairie Baptist Road and Cyntheanne Road has been closed to through traffic as construction continues on the reconstruction of the roadway. Access to the homes and Fire Station #97 will be maintained only to eastbound traffic. Westbound traffic will need to follow the signed detour route. Access into Hunters Run and Silverton is off of Prairie Baptist Road or Cyntheanne Road. See a map of this closure here. PROJECTS SOUTH OF 116TH STREET
96TH STREET LANE RESTRICTIONS As of June 6th, drivers can expect lane restrictions as the contractor has closed the inside lanes for both eastbound and westbound traffic for work on the construction of the Nickel Plate Trail Bridge. There will be one lane for westbound traffic and two lanes for eastbound traffic between Masters Road and Hague Road. Drivers should watch for intermittant lane restrictions. Drivers can expect overnight lane closures on all lanes of 96th street, between Masters Road and Hague Road, on August 6th, 7th, and 8th between 9pm and 6am.
TRAIL CONSTRUCTION
On the week of August 4 the contractor will continue grading and clearing right-of-way along 106th Street from Hamilton Pass to Mollenkopf Road. Drivers on 106th Street between Cumberland Road and Fall Road should expect lane restrictions from 9 AM to 3 PM due to ongoing trail construction. Please plan for potential delays and exercise caution in this area. Crews plan to begin bridge abutment work on the week of August 4 along Hoosier Road, from just north of Blue Meadow Drive to 121st Street. Updates on construction timelines will follow as the contractor refines their schedule. All schedules are weather dependent. 2025 ROAD RESURFACING PROJECT
On the week of August 4 the contractor will be working on the following:
The contractor will be performing paving marking operations on the Lantern Road and 106th street roundabout, Cumberland Road, Hoosier Road on the week of August 11. Flaggers will be on site from 9am to 3pm.
Homeowners will be notified via door hangers prior to any curb reconstruction near their home. After ADA ramp and curb reconstruction is completed, those areas will be restored with topsoil and seed. It is the responsibility of the homeowner to water the seed for the seed to germinate. Following concrete operations contractors will begin performing asphalt road resurfacing and additional notices will be provided. Residents will also be notified via street signage for street parking restrictions. HERITAGE PARK BRIDGE – TRAIL CLOSURE
|