The City of Fishers has changed-up the format of the weekly road construction report. Instead of starting the listing with the State Road 37 and Clear Path updates, it relegates those items to the end, but starts the listing with the expected local road closures.
So, if you are accustomed to the old format, this will be new, but many will see this as a better way to communicate with the public.
With that in mind, here is the Fishers area road construction report, as provided by the City of Fishers, for the work week starting Monday, January 12:
|
|||||
LOCAL ROAD & ROUNDABOUT PROJECTS |
|||||
As the contractor finalizes construction and punchlist items, the contractor plans to utilize periodic lane restrictions and ramp closures. Please use extreme caution while going through this work zone. For additional project information, visit the 146th Street & Allisonville Rd. Project Page.
Due to the unexpected drop in temperatures earlier than anticipated this winter, the westbound lane of 136th Street between Cyntheanne Road and Prairie Baptist Road will remain closed until late spring of 2026. Access to the single homes and the fire station will be maintained for eastbound traffic; however, the road will remain closed to through traffic. Access to Abbott Commons and Silverton will be off of Prairie Baptist Road and access to Hunters Run will be off of Cyntheanne Road or Southeastern Parkway. As weather and temperatures improve, the contractor will be working on what they can accomplish both safely and per specifications. We apologize for any inconvenience that this may cause. See a map of this closure here.
Construction has begun on the widening and reconstruction of 136th Street from Southeastern Parkway to Prairie Baptist Road and is currently in the utility relocation phase. Drivers can expect intermittent lane restrictions during this phase of construction. This project will reconstruct 136th Street from Southeastern Parkway to Prairie Baptist Road from a two-lane rural section to a boulevard section with a raised median and new multi-use paths on both sides of the roadway. New pavement, curb and gutter, and an enclosed storm-sewer system will be installed. For more details visit our Capital Projects Dashboard here.
Fishers Landing Drive will be closed on or after January 12 for the first phase of road construction as a part of the Crew Car Wash project. This closure will be in place on Fishers Landing Drive, between CVS and Jiffy Lube. This road closure will be in place three to four weeks, weather dependent. |
|||||
TRAIL IMPROVEMENTS |
|||||
|
As weather permits, the contractor will be working on final punch-list items along 131st Street and 106th Street. Drivers on 131st Street (from Lantern Road to the Nickel Plate Trail) and 106th Street at Mollenkopf Road should expect lane restrictions from 9 AM to 3 PM. Please plan for potential delays and exercise caution in this area. All work is weather dependent* |
|||||
NEIGHBORHOOD RESURFACING |
|||||
|
Due to the unexpected drop in temperatures earlier than anticipated this winter, paving operations have been paused in Plantana. Homeowners will be notified via door hangers prior to any curb reconstruction near their home. After ADA ramp and curb reconstruction is completed, those areas will be restored with topsoil and seed. It is the responsibility of the homeowner to water the seed for the seed to germinate. Following concrete operations, contractors will begin performing asphalt road resurfacing and additional notices will be provided. Residents will also be notified via street signage for street parking restrictions. For additional project information, view the Capital Project Dashboard here. View the Road Resurface Overview Map here. |
|||||
![]() |
STATE ROAD 37 IMPROVEMENT PROJECTState Road 37 and 141st Street*UPDATE* The eastside of 141st St. at SR37 is currently closed for the next phase of construction. Traffic has transitioned to the westside, with SR37 north and southbound lanes remaining open. Please review detour routes to plan ahead during this time. Thank you for your continued patience and remember to drive cautiously and safely through construction areas. **Please be advised that there is a restriction in place on the eastside of 141st St. (at Mundy Drive near SR37). During this phase, access to the east side of 141st St. will be restricted. This restriction will be in place while crews conduct storm sewer, subgrade treatment, curb construction and pavement work.** All construction updates will be posted to DriveFishers on X(Twitter) and 37Thrives on Facebook. Please visit 37thrives.com to sign-up for email updates. See the detour route here and the business detour route here. To learn more about the State Road 37 Improvement Project and sign up to receive text updates, visit 37Thrives.com. Anticipated Completion: Summer of 2026 |
||||
![]() |
CLEAR PATH IMPROVEMENT PROJECT
The Safe Zones speed control program remains active in the Clear Path construction zone. This program uses automated systems to monitor speeds in specified work zones. The goal of the program is to keep workers, drivers, and their passengers safe by reducing excessive speeding in work zones. It’s important to slow down in construction zones and drive without distractions. Learn more about Safe Zones at SafeZonesIN.com For schedule updates, follow the project on Facebook, X and Instagram, and subscribe to email and text message alerts at ClearPath465.com. Long-Term Closures
82nd Street Ramps For detour routes and additional project information, visit clearpath465.com. |
||||