Fishers Road Construction – Work Week Beginning Monday, October 3rd

There may be a nip in the air as we move into the fall season, but road construction projects will continue around Fishers.  Here’s the schedule for Fishers road work during the work week starting Monday, October 3rd, as provided by the City of Fishers:

==============================================

 

ALLISONVILLE ROAD

Weather permitting, short term lane restrictions will be in place on Allisonville Road between 106th Street and Eller Road from 9 a.m. to 3 p.m. Please use caution when traveling in the area.

CYNTHEANNE ROAD

Road work continues on Cyntheanne Road between Southeastern Parkway and 136th Street, during construction periodic lane restrictions and flaggers will remain in place to help direct traffic.

EXIT FIVE PARKWAY

Exit Five Parkway closed on Tuesday, September 6 to reconstruct the road as part of the 116th Street widening project. The road remains closed to all traffic. Trucks needing to deliver to businesses will need to go up to Cumberland Road to Exit Five Parkway and come in from the north. The road will be closed for approximately two months, and a detour map is available online.

I-69 AND CAMPUS PARKWAY

Milestone Contractors has begun mobilizing cranes and other equipment and setting a temporary concrete barrier wall along I-69 at Campus Parkway Exit 210. Work will require alternating lane closures on northbound and southbound I-69 between 9 p.m. and 6 a.m. Lane closures may recur each night through the end of the week depending on weather and progress. Questions about this project should be directed to INDOT at eastcentralin@indot.in.gov or 1-855-463-6848.

I-69 TRAFFIC RESTRICTIONS

INDOT is overseeing an overnight closure on multiple traffic lanes on I-69 overnight this week. Weather permitting, lane closures, traffic changes and rolling slowdowns of traffic will begin after 9 p.m. and are expected to end before 6 a.m. the next day. Construction schedules and traffic restrictions are subject to change, and questions should be directed to INDOT at indot.carsprogram.org, 1-800-261-ROAD (7623) or 511 from a mobile phone. Please drive with caution as a new traffic pattern is in place.

106th STREET & CUMBERLAND ROAD ROUNDABOUT

Cumberland Road from 106th Street to Mud Creek is closed as Phase 1 of a new roundabout begins. 106th Street will remain open and Cumberland Road north of 106th Street will remain open at this time. The Cumberland Road south of 106th street is closed. Please continue to check the weekly construction update for ongoing progress on this project.

106th STREET INTERCHANGE

INDOT has begun work on the 106th Street interchange. A lane shift is currently in place on I-69 and 106th Street is closed as construction continues. Additional details about this project will be released through INDOT and shared on the weekly construction update. Please be advised the speed limit from 82nd Street to 116th Street has been reduced to 55 mph and there are lane shifts on I-69. Please travel with caution and pay close attention to signage in the area.

116th STREET

There may be short-term lane restrictions on eastbound 116th Street between USA Parkway and Exit Five Parkway while utility work is being completed.

126th STREET

Temporary lane restrictions will be in place on eastbound 126th Street near Pennington Road for curb work on Wednesday, October 5th and Thursday, October 6th. Please travel with caution to help ensure crews are safe while work is completed.