Fishers Road Construction – Work Week Beginning Monday, June 26th

Another long listing of road construction projects in and around Fishers.  A heads-up on Allisonville Road and 146th Street traffic pattern change in the northbound lanes, wit two left turn lanes and one lane northbound.

Below is the complete listing of road work scheduled the work week starting Monday, June 26th, as provided by the City of Fishers

===============================

 

96TH STREET

Construction has begun on the new roundabout at 96th Street and Lantern Road. 96th Street traffic between Kincaid Drive and Fitness Lane/Pinecreek Drive will be reduced to one lane in each direction throughout the summer.

BROOKS SCHOOL ROAD

The Brooks School Road bridge over Interstate 69 is closed as Milestone Contractors rebuild the bridge deck. During the closure, traffic will be detoured to Promise Road via 126th and 136th streets. The bridge will remain closed until August.

ALLISONVILLE ROAD AND 146TH STREET

Hamilton County Highway Department has changed the traffic pattern for northbound Allisonville Road at 146th Street. There are now two left turn lanes and one northbound through lane.

116TH STREET

There will be lane restrictions on 116th Street between I-69 and Cumberland Road throughout the summer in order for the contractor to make improvements to 116th Street.

113TH STREET

Lane restrictions will occur on 113th Street from Olio Road to Florida Road throughout the summer in order for the contractor to resurface and make improvements to the roadway.

126TH STREET

Expect periodic lane restrictions between 9 a.m. and 3 p.m. on 126th Street between Allisonville Road and Lantern Road while the contractor installs passing blisters near Reserve at Lantern. Flaggers will be on site to direct traffic during the restrictions.

I-69 AND CAMPUS PARKWAY

The Campus Parkway interchange was recently shifted into a double-crossover traffic pattern. The interchange will remain under construction through July, when it is expected to be fully open to traffic in its permanent configuration.

Multiple traffic lane shifts will be required to complete construction of the new interchange design. Each phase of remaining construction will bring the interchange closer to its final traffic configuration and capacity. For more information about the new traffic pattern, please visit http://www.in.gov/indot/3441.htm

Milestone Contractors has begun mobilizing cranes and other equipment and setting a temporary concrete barrier wall along I-69 at Campus Parkway Exit 210. Work will require alternating lane closures on northbound and southbound I-69 between 9 p.m. and 6 p.m. Lane closures may recur each night through the end of the week depending on weather and progress. Questions about this project should be directed to INDOT at eastcentralin@indot.in.gov or 1-855-463-6848.

STATE ROAD 37

Construction contractors plan to shift State Road 37 traffic lanes this weekend for a $1.5 million drainage structure construction project between 146th Street and Greenfield Avenue in Noblesville. Northbound lanes are scheduled to be shifted on Friday night, and southbound lanes are scheduled to be shifted Saturday night. Single-lane closures in each direction will be scheduled between 9 p.m. and 6 a.m.

The first phase of construction, which is currently underway, will shift two lanes in each direction toward the right shoulders to provide room for construction in the median. The second phase will shift traffic toward the median to allow construction to be completed along the outside shoulders. All work on the project is expected to be complete this summer.

Starting May 1, geotechnical drilling will begin along the State Road 37 corridor as part of the final design phase of State Road 37 Improvement Project. Lane and shoulder restrictions will be active through the June 30.

Motorists will see staked locations along the corridor starting with the 141st Street intersection. The geotechnical drilling will cause lane restrictions from 131st Street through 146th Street through June 30. Southbound restrictions will not begin until 9 a.m. daily and northbound restrictions will be done daily before 4 p.m. to allow for maximum traffic flow during peak hours.

State Road 37 turn lanes will not be affected during lane closures and crews will maintain a minimum of one through-lane at all times.

The SR37 improvement project is a $124 Million joint project between Fishers, Hamilton Co, Noblesville, and INDOT. Questions or concerns may be directed to drivefishers@fishers.in.us.

OUTSIDE OF FISHERS

The City of Carmel has closed 116th Street and Hazel Dell Parkway for the construction of a roundabout. This closure is expected to last for 75 days. Questions and updates about this project should be directed to the City of Carmel at 317-571-2400.