Lane Restrictions Coming on Part of 116th Street Starting Monday

For those of you using 116th street during the middle of the work day, starting Monday, there will be lane closures on parts of the roadway off-and-on from the City Hall area east to Brooks School Road.  Also beware of some work along some stretches of 126th Street.

Below is the full list of road work for the work week beginning Monday, September 25th.

=============================

 

 

116TH STREET   

Beginning on Monday, September 25 (weather permitting), one lane of westbound 116th Street will be closed between Municipal Drive and Fishers Pointe Boulevard for utility work.

Lane restrictions will be in place between 9 a.m. and 3 p.m. in each direction of 116th Street west of Brooks School Road as crews complete median work in front of Simply Dental. Work is expected to be complete by the end of the week. Signage and flaggers will be present during the restrictions.
Periodic lane restrictions will occur on 116th Street east of Allisonville Road as the contractor repairs concrete curbs and ramps and begins resurfacing work on the roadway. Restrictions will be in place between the hours of 9 a.m. and 3 p.m. Please note that overnight work will occur while traffic volumes are reduced. The City greatly appreciates residents’ patience with construction noise.

126TH STREET   

Possible lane restrictions may occur on 126th Street near Parkside Drive while utility work is completed.

Periodic lane restrictions will occur between 9 a.m. and 3 p.m. on 126th Street between Allisonville Road and Lantern Road as crews complete a passing blister. Flaggers will be present during the restrictions.

I-69   

Improvements are currently underway to rehabilitate existing bridges, pavement and drainage structures along the 15-mile stretch of interstate. Two lanes of traffic in each direction of I-69 are currently shifted to accommodate construction of the additional travel lanes. Signs direct large trucks to use the left lane while traffic is shifted toward the right shoulder through the work zone. The speed limit is reduced to 60 mph and further reduced to 50 mph when workers are present.

I-69 is expected to open to three lanes in each direction between State Road 37 and State Road 38 before the end of this year. Questions about this project should be directed to INDOT at eastcentralin@indot.in.gov or 1-855-463-6848.

STATE ROAD 37   

Geotechnical drilling began along the State Road 37 corridor in May as part of the final design phase of State Road 37 Improvement Project. Lane and shoulder restrictions will be active through September 30. The geotechnical drilling will cause lane restrictions on SR 37 at the 126th Street intersection on or after August 7 and are anticipated to last until September 30. Southbound restrictions begin after 9 a.m. daily and northbound restrictions will be completed daily before 4 p.m. to allow for maximum traffic flow during peak rush hours. Crews will maintain a minimum of one through-lane at all times.

The SR37 improvement project is a $124 million joint project between Fishers, Hamilton County, Noblesville and INDOT. Questions or concerns may be directed todrivefishers@fishers.in.us.

OUTSIDE OF FISHERS   

On or after Monday, August 21, Hamilton County Highway Department will close Cyntheanne Road between 146th Street and 156th Street until December 1, 2017 to replace the bridge over Keiser Drain. Please contact Hamilton County Highway Department at 317-773-7770 with any questions.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.