Road Construction in Fishers for the week of March 6

We are slowly moving into the spring season, even if the weather does not appear that way every day.  With that, be prepared for a number of lane restrictions around Fishers during the work week starting March 6.

Here is the full listing, as provided by the City of Fishers:

==========

STATE ROAD 37 AND 141ST STREETA pre-construction phase at SR 37 & 141st Street is currently in place. During this phase, 141st Street will be a Right-In-Right-Out (RIRO) traffic configuration. This is not the permanent configuration. This will allow for traffic to flow more freely along SR 37 until the next phases of construction can be activated. This will eliminate backups along SR 37 that have caused dangerous stops to the free flow traffic and backups on the 146th Street interchange. Again, this is not the permanent configuration for 141st Street. The full timeline for the 141st Street interchange will be provided after project bids are accepted in the Summer of 2023. View detour routes here.
PROJECTS NORTH OF 116TH STREET
 
131ST STREETComcast is currently doing utility work on 131st Street from Howe Road to Promise Road then north on Promise Road to 141st Street. Lane restrictions will be in place between 9 a.m. and 3 p.m.
PROJECTS SOUTH OF 116TH STREET
 
106TH STREET & HOOSIER ROADUtility relocation is currently taking place at 106th Street and Hoosier Road as part of the roundabout project. For additional project information, view the Capital Project Dashboard here106TH STREET & CUMBERLAND ROADDuring the week of March 6, Duke Energy will be tree trimming on 106th Street between Cumberland Road and Fall Road. Lane restrictions will be in place between 9 a.m. and 3 p.m.ALLISONVILLE ROADDuring the week of March 6, DPW will be performing median landscaping on Allisonville Road between Eller Road and 106th Street. Lane restrictions will be in place between 9 a.m. and 3 p.m.CUMBERLAND ROADDuring the week of March 6, Duke Energy will be tree trimming on Cumberland Road between 106th Street and 116th Street. Lane restrictions will be in place between 9 a.m. and 3 p.m.FLORIDA ROADBeginning on Tuesday, March 7 through Friday, March 10, Florida Road, between Southeastern Parkway and 113th Street, will be closed each day between 9 a.m. and 2 p.m. to allow contractors to make utility crossings. Steel plates will be placed at the end of each day to allow for travel outside of those times. GEIST ROADDuring the week of March 6, Duke Energy will be tree trimming on Geist Road between Fall Creek Road and 106th Street. Lane restrictions will be in place between 9 a.m. and 3 p.m.GEIST GREENWAYPile driving activities are currently taking place near Thorpe Creek as part of the Geist Greenway Project through Monday, March 20. For general project information, please visit https://playfishers.com/299/Geist-Greenway FALL CREEK ROADCitizens Energy Group is mobilizing the lift station on Fall Creek Road near Geist Woods Way, resulting in the closure of Fall Creek Trail in the area until the project is complete in August.