Fishers-area road construction update for the work week staring Monday, April 22

With spring in full swing, the road construction report in and around Fishers remains a long one, mostly updates on ongoing projects.  There is a heads-up on a 5K event coming April 27.

Here is the full listing, as provided by the City of Fishers:

===============

STATE ROAD 37 IMPROVEMENT PROJECT


To learn more about the State Road 37 Improvement Project and sign up to receive text updates, visit 37Thrives.com

STATE ROAD 37 AND 141ST STREET
A pre-construction phase at SR 37 & 141st Street is currently in place. During this phase, 141st Street will be a Right-In-Right-Out (RIRO) traffic configuration.
This is not the permanent configuration. This will allow for traffic to flow more freely along SR 37 until the next phases of construction can be activated. This will eliminate backups along SR 37 that have caused dangerous stops to the free flow traffic and backups on the 146th Street interchange. Again, this is not the permanent configuration for 141st Street. The full timeline for the 141st Street interchange will be provided after project bids are accepted in the Spring 2024. View detour routes here.

View how to merge safely onto Northbound SR 37 from 141st Street here and onto Southbound SR 37 from 141st Street here. To navigate the merge, remember:

  • Use the accel lane to gain speed, not stop
  • Use your mirrors and pay attention
  • Look for a gap in SR 37 traffic and safely merge

 

CHOOSE TO MOVE 5K

 

The Choose to Move 5K will be taking place on April 27, the
opening ceremony will begin at 9AM with ALL races starting
at 9:15 AM. They will have the 5K runners/walkers towards
the front and the 1-mile wialkers towards the back. The
START/FINISH line is located on Saxony Blvd E. This race
will end at the same location, Saxony Blvd E. See a map of
the course here.

For more details on this event you can visit their website,
indianaparkinson.org.
CLEAR PATH IMPROVEMENT PROJECT


To learn more about the Clear Path Improvement Project and sign up to receive text and email updates, visit clearpath465.com 

I-465 & I-69
Drivers will see an increase in construction along the I-69 corridor in the coming months. This work will focus on reconfiguring the interchange at I-465 and I-69. New ramps will provide direct movements from eastbound I-465 and northbound I-465 to northbound I-69. Binford Blvd. will also be reconstructed to separate local traffic from traffic entering and exiting I-69 and I-465. Access to I-69 from Binford Blvd. will remain open.

Crews closed the two ramps at 82nd Street on Monday, January 29. These ramps will remain closed throughout most of 2024.

  • Ramp from I-69 South to 82nd Street
  • Ramp from 82nd Street to I-69 South
The ramp from 82nd Street to I-69 North is open.

The ramp from I-69 North to 82nd Street will remain closed through mid-2024. For detour routes and additional project information, visit clearpath465.com
PROJECTS NORTH OF 116TH STREET

146TH STREET & ALLISONVILLE ROAD – HAMILTON COUNTY PROJECT 
Allisonville Road remains closed north and south of 146th street. Bridge crews are continuing work on the widening of the eastbound bridge over the White River. The contractor is continuing to work on the storm sewer installation, subgrade preparation, and paving operations. The contractor will begin working within existing pavement areas after the new traffic pattern is implemented. Construction vehicles will be entering and exiting from this work area, so please be vigilant when driving through the contsruction zone.

The contractor will occasionally utilize a lane restriction for the delivery of materials in the work area (from 9AM to 3PM). These lane restrictions will take place in the left-hand westbound lane of 146th Street.

For additional project information, visit the 146th street and Allisonville rd. Project Page. 

90-DAY ALLISONVILLE ROAD CLOSURE

Please be advised, the contractor has closed Allisonville Road between 146th Street and Kensington Drive, and between 146th Street and Helmsley Court. This will remain closed for 90 calendar days. Property owners within the limits of the closure of Allisonville Road will have access to their property during the closure. Both eastbound and westbound 146th Street will open to all through traffic throughout the closure of Allisonville Rd. The contractor will be placing detour route markers as we approach the road closure. Please utilize the posted detour route to avoid the road closures on Allisonville. View the road closure and detour route here.

PROJECTS SOUTH OF 116TH STREET
ROAD CLOSURE – 96TH STREET AND ALLISONVILLE ROAD INTERSECTION
On April 1st,construction began on the 96th St. & Allisonville Rd. Roundabout Project.
This project aims to enhance connectivity along this stretch of the Allisonville Corridor.
The existing Michigan Left intersection was eliminated and transitioned to a two-lane
roundabout adjacent to the new River Place development. This project is slated to be
completed at the end of the year, with minor enhancements completed in the Spring
of 2025. You can view a close up map of what the roundabout will look like after
April 9 here.

Here’s what to expect:

Closures – After April 9, 2024

  • 96th Street is closed from Allisonville Road to Hazel Dell Pkwy.
  • Southbound traffic cannot turn left onto 96th St from Allisonville Rd.
  • Allisonville Rd is open to one lane at 96th Street for North and Southbound traffic.
  • All access to local businesses remains open.
  • See suggested detour maps at 96th & Allisonville Rd Roundabout
ROAD CLOSURE – BRIDGE 187 (106TH STREET OVER MUD CREEK)- HAMILTON COUNTY PROJECT

Please be advised, 106th Street between Cumberland Road and Hamilton Pass has been closed to all thru traffic for a bridge replacement project. The anticipated roadway reopening date is Friday, October 18, 2024.

Local traffic will continue to have access to their homes, while thru traffic is asked to utilize the posted detour route of Cumberland Road, 96th Street, and Mollenkopf Road. For more details visit the Hamilton County page.


HERITAGE PARK BRIDGE – TRAIL CLOSURE 
The City of Fishers has partnered with the City of Carmel, Clay Township, Carmel Clay Parks and Recreation , Hamilton County, and Delaware Township to connect Heritage Park at White River and Carmel’s Hazel Landing Park with a bridge over White River. This new amenity will provide enhanced connectivity between the two communities, as well as new recreational opportunities for our residents. To construct this bridge, the contractor will need to restrict access to a portion of Heritage Park’s loop trail that runs adjacent to the river through the woods beginning the week of March 4, click here for an ariel view. During this time, you’ll notice temporary construction fencing going up as we prepare for construction. Beginning the week of March 11, the contractor will work to clear the necessary trees between the park and river. Bridge construction will follow beginning in May. Construction is expected to occur Monday through Saturday beginning at 7 a.m. The bridge is expected to be complete in August 2025.

BARRETT LAW EAST AND WEST

Parkside/Publishers

Road work is scheduled to begin at Barrett East the week of Monday, April 15. As crews work from the south end of the project to the North, towards 131st street, there will be lane restrictions in place. The roadway will not be closed and access will be maintained to all businesses. Ultimately, all three roadways of Parkside, Publishers, and Enterprise will be addressed between 126th and 131st. This project, weather permitting, will be completed in approximately 1 to 1 and a half weeks.

Fishers Trade Center 

The contractor has located and marked all utilities and the “potholing” of those utilities is scheduled to begin on April 18. Once utilities are located, work on phase 1 will begin, which includes reconstruction of Britton Park Road (South of the fork) and Trade Center Drive. Road construction is scheduled to begin on April 22. Access to businesses will be maintained during the project. 

SIDEWALK IMPROVEMENT PROJECT 

Howard Companies is currently working in the Tanglewood Neighborhood.

This work will only consist of removal and replacement of sidewalk panels which pose a toe kick trip hazard. Sidewalk within driveways is not included in the scope of this project.

2022 THOROUGHFARE DRAINAGE IMPROVEMENTS- AREA 3 – INDIANAPOLIS PROJECT


Phase 1 of this plan required closure of Masters Road, the anticipated closure dates will be March 25 to April 22. These restrictions will affect through traffic of Master Road between 91st and 96th Street. Click here to view a map of this detour.

Phase 2 is anticipated to take place from April 22 to June 6, during this phase there will be a one lane closure between 91st street and 96th Street. Click here to view a map of this detour.

For more info visit Indianapolis Thoroughfare Drainage Improvements – Area 3 page.

One thought on “Fishers-area road construction update for the work week staring Monday, April 22

  1. The simultanious closures of Masters Rd. and Allisonville/96th st. shows a significant lack of coordination between Fishers and Indianapolis.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.