The road construction season is in full gear and all the major summer projects are ongoing. The list is long, so I would urge motorists to keep a close eye on the listing for the coming week.
Here is the full report for the week starting Sunday, June 7, as provided by the City of Fishers:
🚩Upcoming Construction Updates – At a Glance🚩
|
|
| MAJOR CLOSURES AND DETOURS | |
|
96th Street & Cyntheanne Road – CLOSURE IN PLACE Construction of the new roundabout at 96th Street and Cyntheanne Road has begun and a full closure is in place at this roundabout. What Drivers Should Expect
Utility relocation work is already underway ahead of construction activities. View the detour route here. 136th Street Widening – Southeastern Parkway and Prairie Baptist Road The 136th Street Widening Project has transitioned into Phase 2 This next phase will focus on improvements between Southeastern Parkway and Prairie Baptist Road. As construction progresses, 136th Street will be closed to through traffic within the project limits. Drivers should follow the signed detour route using Southeastern Parkway and Prairie Baptist Road to reconnect with 136th Street. This major improvement project will transform 136th Street from a rural two-lane roadway into a modern boulevard featuring: • Raised medians • New multi-use paths on both sides of the road • New pavement, curb & gutter • Storm sewer infrastructure upgrades Motorists should expect changing traffic patterns and additional travel time in the area and follow posted detour signage. Please drive cautiously and stay alert near work zones. View detour map here. Road Improvements at 116th Street & Allisonville Road Project Update Traffic down to one lane in all directions, drivers should seek alternate route. Drivers can expect to see construction begin beginning on the week of June 8. What’s Happening The City of Fishers is improving the intersection of 116th Street and Allisonville Road to enhance traffic flow and safety. While the project was originally planned as a roundabout, additional analysis showed the improvements could be achieved through less invasive roadway changes. Construction is expected to continue through October 2026, weather and material availability permitting. What to Expect
Initial work includes construction signage and signal-related activity, followed by intersection improvements, curb and ramp work, sidewalk work, and paving later in the season. Lantern Road at Morgan Drive From June 8-19 Lantern road will be closed at Morgan Drive, detour signs will be posted for drivers. Please seek an alternate route.
|
|
| UTILITY WORK | |
| Cumberland Road Utility Work
Lane restrictions continue between 106th Street and 116th Street from 9 a.m. to 3 p.m.
Brightspeed Fiber Installation Brightspeed will be installing fiber throughout Avalon of Fishers this week. Work will be conducted in utility easements behind the sidewalk.
|
|
| PROJECT UPDATES | |
|
Neighborhood Resurfacing Concrete curb and ADA ramp work continues next week in Rosewood, weather permitting. Milling and resurfacing operations will follow. Milling/paving operations in Sunblest then Sumerlin Trails. Whats Next: Concrete operations on Harrison Parkway (Weaver Woods North) following Rosewood. Residents should expect:
Southeastern Parkway & Olio Road Roundabout Improvements The City of Fishers will begin reconstructing the roundabout at Southeastern Parkway and Olio Road in mid-June to improve safety and traffic flow at one of the region’s busiest intersections, which has a history of frequent non-fatal crashes. The project will be completed in November 2026 during 3 phases. The project will add more room for vehicles, reduce backups on nearby roads, and make the roundabout easier to navigate. When completed this fall, the roundabout will help drivers choose the correct lane sooner, move through the intersection more safely, and reduce rear-end and side-swipe crashes. Phase 1 – Mid-June – Late July The roundabout will remain open with lane restrictions. Crews will improve nearby 136th Street and permanently make it a two-way road, providing a detour option during Phase 2. They will also build a new connection road between 136th Street to the west for easier westbound traffic flow. Alternate routes are encouraged but not required during Phase 1.
More information and traffic maps will be announced before construction starts.
|
|
| COMMUNITY EVENT | |
|
Touch-A-Truck Rescheduled for June 8 Fishers’ annual Touch-A-Truck event returns to the Nickel Plate District Amphitheater from 4 to 7 p.m. Temporary road closures and parking impacts are expected near Municipal Drive during the event. Learn more at Fishers Parks Touch-A-Truck
|
|
| 🚗 REGIONAL CONSTRUCTION | |
| Hamilton County Highway Department
PERIODIC LANE RESTRICTIONS– 146th Street and Allisonville Road Hamilton, Indiana – Please be advised, beginning on or after, Monday, June 1,2026, drivers should expect periodic lane restrictions for median landscaping / final miscellaneous work for the next upcoming weeks. Drivers should expect increased construction traffic in the work zone. When driving through the construction zone, drivers are encouraged to be vigilant and watch for flaggers. Please use extreme caution and follow the posted work zone speed limit while driving through this construction zone.
EAST CARMEL PEDESTRIAN SAFETY IMPROVEMENTS: April 1 – early August As of April 1, extensive work has begun on the east side of Carmel to install raised pedestrian crosswalks within several roundabouts along Hazel Dell Parkway and Gray Road. Phase 1 (30-day closure) 126th Street and Hazel Dell Parkway – Complete Phase 2 (30-day closure) – Complete 126th Street and Gray Road Phase 3 (30-day simultaneous closures, summer break) June 4 to July 3 Cherry Creek Boulevard and Hazel Dell Parkway 116th Street and Gray Road Phase 4 (46-day closure, summer break) July 3 – August 10 116th Street and Hazel Dell Parkway Phase 5 (30-day closure) TBD Main Street and Gray Road All raised pedestrian crosswalk installations are set for completion in September, reinforcing Carmel’s ongoing commitment to student and neighborhood safety. For more details visit the City of Carmels website.
|
|
| STATE ROAD 37 IMPROVEMENT PROJECT
STATE ROAD 37 IMPROVEMENT PROJECT 🛣️State Road 37 and 141st Street🎆 The State Road 37 Improvement Project at 141st Street is now substantially complete, and the City celebrated the official ribbon cutting for the new interchange on May 26. Motorists should expect periodic lane restrictions and intermittent work activity throughout the corridor as contractors complete final punch-list items and remaining project details, including landscaping and minor finishing work. Drivers are encouraged to continue using caution in the area while crews complete these final activities. |
|
| CLEARPATH IMPROVEMENT PROJECT
Upcoming Short-Term Closures Friday, June 5 at 6 a.m. to Sunday, June 7 at 6 a.m.
Friday, June 5 at 9 p.m. to Saturday, June 6 at 6 a.m.
Friday, June 5 at 9 p.m. to Sunday, June 7 at 6 a.m.
Long-Term Closures
82nd Street Ramps 82nd Street ramps – current configuration
|
|