Fishers Weekly Road Construction Update: What Drivers Need to Know

The City of Fishers has released its weekly construction report, and the biggest impact this weekend is a full closure of the 96th Street and Cyntheanne Road roundabout on Saturday, August 8, while crews mill and pave. Signed detours will route traffic around the intersection, with local access maintained. Weather permitting, the roundabout reopens Monday, August 10.

Also on Saturday, drivers near Launch Fishers should expect temporary restrictions during Hamilton Humane’s Woofstock 5K & Dog Walk. Morning delays are possible.

Several long-term projects continue. The 136th Street Widening Project has moved into Phase 2 between Southeastern Parkway and Prairie Baptist Road, where 136th Street is closed to through traffic. The project will convert the rural two-lane road into a boulevard with raised medians, multi-use paths on both sides, new pavement and curb, and upgraded storm sewers.

At 116th Street and Allisonville Road, outside lanes remain closed with traffic shifted to inside through lanes and turn lanes — a pattern expected to hold through early October. As of August 5, the west leg of Fishers Crossing Boulevard at Allisonville Road closed for roughly three weeks, blocking that entrance to the shopping center. All businesses remain open.

The USA Parkway Widening Project north of 106th Street brings lane restrictions through October, with substantial completion expected in mid-October. Work includes widening, new curbs, trail construction, and resurfacing.

At the Southeastern Parkway and Olio Road roundabout, lane restrictions begin in early August, including Olio Road reduced to one lane each direction and closure of the roundabout’s “5th leg.”

Utility work continues on Cumberland Road between 106th and 116th streets from 9 a.m. to 3 p.m. AT&T begins fiber installation in Beaver Ridge, Pine Bluff Overlook, Bradford Ridge, Walnut Creek, Delaware Pointe, Summerfield, and Delaware Crossing. Brightspeed starts fiber work in The Boulders, Reserve at Steeplechase, Sanctuary at Steeplechase, and Oakhurst.

Resurfacing crews begin concrete operations in Fawnsbrook the week of August 10, with milling and base repair coming to 96th Street from Carroll to Olio roads and Westmoreland Drive in Somerset.

Regionally, Cumberland Road south of 116th Street has daily lane restrictions through August 21 for bridge work, and I-465 ClearPath closures are scheduled nightly August 10–14.

Full report as provided by the City of Fishers is below:

Road Closures and Traffic Impacts – At a Glance
  • USA Parkway Widening – Lane restrictions through October
  • 96th Street & Cyntheanne Road – Full intersection closure on August 8 for paving
  • 136th Street Widening – Detour in place between Southeastern Parkway & Prairie Baptist Road
  • 116th Street & Allisonville Road – One lane in each direction (Traffic Phase 2)
  • Southeastern Parkway & Olio Road Roundabout – Periodic lane restrictions
  • Fishers Crossing Blvd – Closed west of Allisonville Road through end of August
 Woofstock 2026 – Saturday, August 8
Motorists should expect temporary traffic restrictions starting at Launch Fishers on Saturday, August 8, as Hamilton Humane hosts the annual Woofstock 5K & Dog Walk. Delays are possible during the morning event. Please follow posted signage, use caution, and consider alternate routes if traveling through the area. A detour map is provided on their website.
Major Closures and Detours
 

96th Street & Cyntheanne Road

A roundabout at 96th Street and Cyntheanne Road has been constructed to replace the former intersection.

UPCOMING WORK

The contractor will be milling and paving this roundabout on Saturday, August 8, drivers can expect the roundabout to be fully closed during operations.Weather permitting the roundabout will open back up to traffic on Monday, August 10.

Detour Map

What Drivers Should Expect

  • Full intersection closure to traffic (Saturday August 8th)
  • Signed detour routes around the intersection
  • Local access maintained for nearby properties
  • Additional travel time in the area
  • Periodic lane restrictions or closures as the final items are completed on this project.

View the detour route here.

 

 136th Street Widening – Southeastern Parkway and Prairie Baptist Road

 

The 136th Street Widening Project has transitioned into Phase 2 This next phase will focus on improvements between Southeastern Parkway and Prairie Baptist Road.

136th Street is closed to through traffic within the project limits. Drivers should follow the signed detour route using Southeastern Parkway and Prairie Baptist Road to reconnect with 136th Street.
This major improvement project will transform 136th Street from a rural two-lane roadway into a modern boulevard featuring:

• Raised medians
• New multi-use paths on both sides of the road
• New pavement, curb & gutter
• Storm sewer infrastructure upgrades

Motorists should expect changing traffic patterns and additional travel time in the area and follow posted detour signage. Please drive cautiously and stay alert near work zones.

View detour map here.

Detour Map

 

Road Improvements at 116th St & Allisonville Rd

Traffic Shift Update and Road Closure

Fishers Crossing Access Closure

As of August 5, the west leg of Fishers Crossing Blvd at Allisonville Road has been closed for approximately next three weeks, weather permitting.

During the closure, motorists will not be able to enter or exit the Fishers Crossing Shopping Center area at this connection to Allisonville Road. Drivers should use an alternate entrance and follow posted signage.

This closure is necessary to support ongoing construction for the 116th Street and Allisonville Road Improvement Project.

As of Thursday, July 16, crews have implemented the next major traffic shift as construction continues at the 116th Street and Allisonville Road intersection.

What to Expect

  • The outside lanes at the intersection will be closed.
  • Traffic will be shifted to the inside through lanes and designated turn lanes.
  • All businesses will remain open and accessible throughout construction.
  • This traffic pattern is expected to remain in place through early October, weather permitting.

Motorists are encouraged to slow down, use caution, follow posted signage, and allow extra travel time when traveling through the area.

Stay Connected

For the latest construction updates:

  • Drive Fishers Road Construction Updates: FishersIN.gov/RoadConstruction
  • Follow @DriveFishers on X
  • Subscribe to the Drive Fishers Newsletter: FishersIN.gov/Subscribe
  • Subscribe to the Allisonville Corridor Newsletter: FishersIN.gov/Allisonville

Questions? Contact the Engineering Department at drivefishers@fishersin.gov.

Utility Work
Cumberland Road Utility Work – Duke Project

Lane restrictions continue between 106th Street and 116th Street from 9 a.m. to 3 p.m.

ATT Utility Work

ATT will be installing fiber throughout the following neighborhods: Beaver Ridge, Pine Bluff Overlook, Bradford Ridge, Walnut Creek, Delaware Pointe, Summerfield, Delaware Crossing. Work will be begin in the next week and will be conducted in utility easements behind the sidewalk.

Upcoming Brightspeed Fiber Installation

Brightspeed is expected to begin fiber installation work next week in the following neighborhoods:

  • The Boulders
  • Reserve at Steeplechase
  • Sanctuary at Steeplechase
  • Oakhurst

Residents may notice door hangers being distributed and utility locate flags appearing in advance of construction. These are part of the preparation process before work begins. For more information on Fiber installation and what you can expect, please visit https://fishersin.gov/services-resources/resident-resources/homeowners-associations/

Project Updates
USA Parkway Widening Project (North of 106th Street)

Motorists should expect lane restrictions on USA Parkway north of 106th Street as construction begins on the USA Parkway Widening Project. Lane restrictions are expected to remain in place through October, weather permitting.

Work will include roadway widening, new curb improvements, trail construction, and pavement resurfacing. Traffic will be maintained throughout construction, and access to businesses and driveways will remain open. Motorists should expect periodic traffic shifts, reduced speeds, and occasional delays while crews work.

The project is anticipated to reach substantial completion in mid-October, with final restoration and punch list work continuing into November.
Please slow down, watch for construction crews, and allow extra travel time when traveling through the area. As always, schedules are weather dependent and subject to change.

 

Resurfacing Projects:

Road Resurfacing and Trail Work Update

On the week of August 10:

The contractor will begin concrete operations in Fawnsbrook neighborhood ahead of milling and paving.

Upcoming work includes milling and base repair on 96th Street from Carroll Road to Olio Road and Westmoreland Dr. in the Somerset neighborhood. All work is weather dependant.

Homeowners will be notified via door hangers prior to any curb reconstruction near their home. After ADA ramp and curb reconstruction is completed, those areas will be restored with topsoil and seed. It is the responsibility of the homeowner to water the seed for the seed to germinate. Following concrete operations contractors will begin performing asphalt road resurfacing and additional notices will be provided. Residents will also be notified via street signage for street parking restrictions.

For additional project information, view the Capital Project Dashboard here.

Capital Projects Dashboard

 

Southeastern Parkway & Olio Road Roundabout Improvements

Construction is underway on the Southeastern Parkway and Olio Road roundabout to improve safety and traffic flow at one of the region’s busiest intersections.

Currently, the roundabout remains open with no lane restrictions through early August. Olio Road is reduced to one lane southbound.
Beginning in early August, drivers should expect lane restrictions, including Olio Road reduced to one lane in each direction and closure of the “5th leg” of the roundabout.
Detour and traffic maps for Phase 2 will be shared before that phase begins in October. Details: fishersin.gov/olio

🚗 Regional Construction
Hamilton County Highway Department

LANE RESTRICTIONS – CUMBERLAND ROAD – BRIDGE 164 OVER MUD CREEK

Please be advised, on Thursday, August 6, 2026, drivers should expect daily lane restrictions on Cumberland Road, south of 116th Street, for bridge preservation work. The expected completion date for this project is Friday, August 21, 2026. Please use extreme caution while driving through the construction zone. Drivers are encouraged to be vigilant and watch for flaggers in the area.

East Carmel Pedestrian Safety Improvements:

April 1 – early August
As of April 1, extensive work has begun on the east side of Carmel to install raised pedestrian crosswalks within several roundabouts along Hazel Dell Parkway and Gray Road.
Phase 4 (46-day closure, summer break) NOW OPEN
116th Street and Hazel Dell Parkway
Phase 5 (30-day closure) TBD
Main Street and Gray Road
All raised pedestrian crosswalk installations are set for completion in September, reinforcing Carmel’s ongoing commitment to student and neighborhood safety.
For more details visit the City of Carmels website.

Carmel Updates

STATE ROAD 37 IMPROVEMENT PROJECT

 

🛣️State Road 37 and 141st Street🎆

 

The State Road 37 Improvement Project at 141st Street is now substantially complete, and the City celebrated the official ribbon cutting for the new interchange on May 26.

 

Motorists should expect periodic lane restrictions and intermittent work activity throughout the corridor as contractors complete final punch-list items and remaining project details, including landscaping and minor finishing work.

 

Drivers are encouraged to continue using caution in the area while crews complete these final activities.

CLEARPATH IMPROVEMENT PROJECT

Upcoming Short-Term Closures

Drivers can expect the following closures:

Friday, August 7 (9 p.m. to 6 a.m.)

  • Eastbound I-465 reduced to two lanes from Keystone Avenue to White River

Saturday, August 8 (6 a.m. to 1 p.m.) 

  • Westbound 75th street at Binford Blvd.  single lane closure.

Monday, Aug. 10 – Friday, August 14 (nightly 9 p.m. to 6 a.m.)

  • Northbound I-465 single lane closure  from Fall Creek to the I-69 interchange.

Long-Term Closures

82nd Street Ramps
82nd Street ramps – current configuration

New lanes of I-465, Allisonville Road ramp NOW OPEN

Click HERE to learn more.