Fishers road work brings new closures, paving the week of Sept. 28

Changes at the Southeastern Parkway and Olio Road roundabout lead the latest Fishers road construction report, with a permanent closure scheduled for the week of Sept. 28 as work continues across the city.

According to the city’s weekly update, the roundabout’s fifth leg will permanently close to traffic that week. Olio Road will be reduced to one lane in each direction between the roundabout and a point just south of 136th Street.

As part of that work, 136th Street west of Olio Road will close for approximately three weeks, with traffic detoured using 134th Street. Access from I-69 to IU Health Fishers will remain open via the bypass lane, and emergency access will be maintained.

Elsewhere on 136th Street, the widening project has moved into its second phase between Southeastern Parkway and Prairie Baptist Road. That stretch remains closed to through traffic, with a signed detour using those two roads.

At 116th Street and Allisonville Road, traffic remains limited to one through lane in each direction, with designated turn lanes. That arrangement is expected to continue through early October, weather permitting. The east leg of Fishers Crossing Boulevard at Allisonville Road is also closed for paving, requiring drivers headed to Fishers Station to use another entrance. Businesses remain open.

Resurfacing crews plan to pave 96th Street between Carroll and Olio roads during the week of Sept. 28, following milling and base repairs. Flaggers will direct traffic as work moves east to west. Milling is also scheduled to begin that week in Springs of Cambridge.

Lane restrictions continue on USA Parkway north of 106th Street through October. Utility relocation at 131st Street and Brooks School Road may cause periodic restrictions as preparations continue for a new roundabout.

Drivers should allow extra travel time and follow posted detours. Construction schedules are weather dependent and subject to change.

The full report, including utility work, neighborhood projects and Clear Path traffic restrictions, follows below:

Road Closures and Traffic Impacts – At a Glance
  • USA Parkway Widening – Lane restrictions through October
  • 136th Street Widening – Detour in place between Southeastern Parkway & Prairie Baptist Road
  • 116th Street & Allisonville Road – One lane in each direction (Traffic Phase 2) – Fishers Station Access Closure
  • Southeastern Parkway & Olio Road Roundabout – On the week of September 28 the fifth leg of the roundabout will permanently close to traffic as work progresses on the new roundabout configuration.
  • 131st and Brooks School Road – Utility relocation in progress – periodic lane restrictions are possible
Major Closures and Detours
136th Street Widening – Southeastern Parkway and Prairie Baptist Road

 

The 136th Street Widening Project has transitioned into Phase 2 This next phase will focus on improvements between Southeastern Parkway and Prairie Baptist Road.

 

136th Street is closed to through traffic within the project limits. Drivers should follow the signed detour route using Southeastern Parkway and Prairie Baptist Road to reconnect with 136th Street.

This major improvement project will transform 136th Street from a rural two-lane roadway into a modern boulevard featuring:

 

  • Raised medians
  • New multi-use paths on both sides of the road
  • New pavement, curb & gutter
  • Storm sewer infrastructure upgrades

 

 

Motorists should expect changing traffic patterns and additional travel time in the area and follow posted detour signage. Please drive cautiously and stay alert near work zones.

 

View detour map here.​

Detour Map​

 

Road Improvements at 116th St & Allisonville Rd

Fishers Station Access Closure

The East leg of Fishers Crossing Blvd at Allisonville Road has been closed in order to pave.

During the closure, motorists will not be able to enter or exit the Fishers Station Shopping Center area at this connection to Allisonville Road. Drivers should use an alternate entrance and follow posted signage.

Additionally, sidewalks within the project area are closed.

This closure is necessary to support ongoing construction for the 116th Street and Allisonville Road Improvement Project. Crews are currently reconstructing the west side of Allisonville Road at Fishers Crossing Drive as part of this work.

Current Construction Activity

While construction activity may not always be visible from every part of the project area, the contractor continues to work throughout the project limits in several locations at once. Current work includes:

  • Replacing driveway approaches
  • Painting streetlights
  • Installing temporary traffic signals
  • Reconstructing the roadway on the west side of Allisonville Road at Fishers Crossing Drive

Drivers may see crews and equipment shifting between different areas of the project as this work progresses.

As of Thursday, July 16, crews implemented the next major traffic shift as construction continues at the 116th Street and Allisonville Road intersection.

What to Expect

  • The outside lanes at the intersection will be closed.
  • Traffic will be shifted to the inside through lanes and designated turn lanes.
  • All businesses will remain open and accessible throughout construction.
  • This traffic pattern is expected to remain in place through early October, weather permitting.

Motorists are encouraged to slow down, use caution, follow posted signage, and allow extra travel time when traveling through the area.

Stay Connected

For the latest construction updates:

  • Drive Fishers Road Construction Updates: FishersIN.gov/RoadConstruction
  • Follow @DriveFishers on X
  • Subscribe to the Drive Fishers Newsletter: FishersIN.gov/Subscribe
  • Subscribe to the Allisonville Corridor Newsletter: FishersIN.gov/Allisonville

Questions? Contact the Engineering Department at drivefishers@fishersin.gov.

Utility Work
Cumberland Road Utility Work – Duke Project

Lane restrictions continue between 106th Street and 116th Street from 9 a.m. to 3 p.m.

 

ATT Utility Work

 

ATT will be installing fiber throughout the following neighborhods: Beaver Ridge, Pine Bluff Overlook, Bradford Ridge, Walnut Creek, Delaware Pointe, Summerfield, Delaware Crossing. Work will be begin in the next week and will be conducted in utility easements behind the sidewalk. Att has been working in the in the Limesprings Neighborhood.

 

Upcoming Brightspeed Fiber Installation

 

Brightspeed is expected to begin fiber installation work next week in the following neighborhoods:

  • The Boulders
  • Reserve at Steeplechase
  • Sanctuary at Steeplechase
  • Oakhurst

 

Residents may notice door hangers being distributed and utility locate flags appearing in advance of construction. These are part of the preparation process before work begins.

 

 

For more information on Fiber installation and what you can expect, please visit https://fishersin.gov/services-resources/resident-resources/homeowners-associations/​

Project Updates
 

131st and Brooks School Road Roundabout

 

A new roundabout will be constructed at the intersection of 131st Street and Brooks School Road. Drivers can expect periodic lane restrictions in the current utility relocation phase.

 

USA Parkway Widening Project (North of 106th Street)

 

Motorists should expect lane restrictions on USA Parkway north of 106th Street as construction begins on the USA Parkway Widening Project. Lane restrictions are expected to remain in place through October, weather permitting.

 

Work will include roadway widening, new curb improvements, trail construction, and pavement resurfacing. Traffic will be maintained throughout construction, and access to businesses and driveways will remain open. Motorists should expect periodic traffic shifts, reduced speeds, and occasional delays while crews work.

The project is anticipated to reach substantial completion in mid-October, with final restoration and punch list work continuing into November.

 

Please slow down, watch for construction crews, and allow extra travel time when traveling through the area. As always, schedules are weather dependent and subject to change.

 

Resurfacing Project

Road Resurfacing Update

 

Crews are making significant progress on the City’s 2026 resurfacing program, with work substantially complete in several neighborhoods and along major roadways.

 

Resurfacing Package 26-1

Resurfacing is substantially complete in Sunblest, Summerlin Trails, Rosewood, Weaver Woods, Weaver Woods North, Fawnsbrook, and on Westmoreland.

Residents may still see crews returning to these areas to complete final items.

On the week of September 28, crews will continue work on 96th Street from Carroll Road to Olio Road. Milling is scheduled to begin on Friday September 25 followed by base repair then paving the week of the 28th with striping and pavement markings to follow. Crews will work East to west with flaggers present to help direct traffic.

Resurfacing Package 26-2

Roadway work is substantially complete on 131st Street, Howe Road, and Promise Road, with final pavement markers still to be installed. Some additional final punch list items also remain at Promise Road and 126th Street.

Crews will begin milling in the Springs of Cambridge neighborhood on the week of September 28.

Drivers may continue to see crews completing final work in resurfaced areas. Please slow down, watch for workers and equipment, and follow posted traffic restrictions.

As always, construction schedules are weather dependent and subject to change.

For additional project information, view the Capital Project Dashboard here.​

 

 

Capital Projects Dashboard​

 

Southeastern Parkway & Olio Road Roundabout Improvements

 

Construction is underway on the Southeastern Parkway and Olio Road roundabout to improve safety and traffic flow at one of the region’s busiest intersections.

On the week of September 28 the fifth leg of the roundabout will permanently be closed to traffic.

Olio Road will be reduced to one southbound lane exiting the roundabout and one northbound lane entering the roundabout. This lane reduction will extend from the roundabout to just south of 136th Street.

As part of this phase of work, 136th Street west of Olio Road will also close for approximately three weeks. This closure will allow crews to complete tie-in work for the new two-way section of 136th Street and the bypass lane from Southeastern Parkway.

During the closure, traffic will be detoured using 134th Street. This detour map provides the designated route and can be shared with clients, patients and staff who may be traveling to the area.

Access from I-69 to IU Health Fishers will remain open via the bypass lane, and emergency access will be maintained throughout the closure.

The project remains on track for Phase 2 to begin in mid-October. Additional project updates, traffic impacts and detour information are available at https://fishersin.gov/olio​

More Details​

CLEARPATH IMPROVEMENT PROJECT

KNOW BEFORE YOU GO: What to Expect –Click Here Southbound I-69 now in final configuration

Upcoming Short-Term Closures

Saturday, Sept. 26 (7 a.m. to 5 p.m.)

  • Far right lane closed on northbound I-465 from Fall Creek to 75th Street

Sunday, Sept. 29 — Friday, Oct. 2

  • Corridor-wide mobile shoulder cleaning

Mid-September through Mid-October 

  • The ramp from southbound I-69 to southbound Binford Boulevard temporarily reduced to one lane

 

Long-Term Closures

  • Ramp from northbound Binford Boulevard to westbound I-465 closed

 

82nd Street Ramps

 

For more information Visit the Clearpath465 website.