A key stretch of 136th Street in Fishers reopened to through traffic Friday night. Drivers still face major detours at the Southeastern Parkway and Olio Road roundabout, according to the city’s weekly construction update.
The widened section of 136th Street between Southeastern Parkway and Prairie Baptist Road reopened Nov. 6. Crews are still finishing the project, so drivers may run into some lane restrictions.
Fall Recycling Day today
Fishers residents can drop off electronics, appliances, paint, household hazardous waste and other items today, Saturday, Nov. 7, from 8 a.m. to 1 p.m. at Billericay Park. Paper recycling and document shredding will also be offered. The event is for residents only, and fees apply for some materials above set limits.
Olio Road roundabout
Phase 2 of the Southeastern Parkway and Olio Road roundabout reconstruction is expected to continue through the end of the year. The roundabout connections for north-south travel on Olio Road are closed, and the roundabout’s fifth leg has closed permanently.
Southbound drivers on Olio Road cannot continue south through the roundabout. They are directed west onto Campus Parkway/146th Street. Northbound drivers must detour on 136th Street and use the newly built connection to Southeastern Parkway. Eastbound drivers will use a bypass lane toward IU Health Fishers to reach the 136th Street roundabout. One westbound lane stays open for drivers headed west or north on Olio Road.
City officials say nearby businesses, hospitals and medical offices remain open. They expect significant delays, especially at peak hours. Detour maps are posted at FishersIN.gov/Olio.
Other projects
- 116th Street and Allisonville Road: Milling and paving are done. Lane restrictions will continue while crews finish striping, traffic signal work and sidewalk concrete. Sidewalks in the project area stay closed.
- USA Parkway north of 106th Street: The widening is substantially complete. Lane restrictions are expected through the end of November.
- 131st Street and Brooks School Road: Utilities are being relocated ahead of a new roundabout, and drivers may see periodic lane restrictions.
- Resurfacing: Package 26-1 is substantially complete, with striping still to come. Crews are finishing Package 26-2 work in the Springs of Cambridge neighborhood.
Utility and fiber work
Duke Energy work on Cumberland Road between 106th and 116th streets keeps lanes restricted from 9 a.m. to 3 p.m.
AT&T plans to begin fiber installation this coming week in Beaver Ridge, Pine Bluff Overlook, Bradford Ridge, Walnut Creek, Delaware Pointe, Summerfield and Delaware Crossing. Brightspeed is expected to start this coming week in The Boulders, Reserve at Steeplechase, Sanctuary at Steeplechase and Oakhurst. Residents may notice door hangers and utility flags before work begins.
ClearPath 465
On the Indianapolis side, the ClearPath project has overnight lane closures on 75th Street and Binford Boulevard tonight from 9 p.m. to 6 a.m. Knue Road is closed at the Nickel Plate Trail crossing through late November. The ramp from northbound Binford Boulevard to westbound I-465 is closed long-term.
All construction schedules depend on the weather and may change.
The full city report follows:
| Road Closures and Traffic Impacts – At a Glance | |
|
|
| Fall Recycling Day | Saturday, November 7
Fishers residents can drop off electronics, appliances, paint, household hazardous waste, and more at Billericay Park from 8 a.m. to 1 p.m. Paper recycling and off-site confidential document shredding will also be available. This event is for residents only; business materials will not be accepted. Fees apply for certain materials above specified limits. |
|
| Major Closures and Detours | |
| 136th Street Widening – Southeastern Parkway and Prairie Baptist Road
136th Street between Southeastern Parkway and Prairie Baptist Road will reopen to through traffic tonight, Friday, November 6. Drivers may encounter intermittent lane restrictions as crews complete final work on the widening project. Please continue to use caution, follow posted signage, and stay alert for crews working in the area.
Road Improvements at 116th St & Allisonville Rd *Open but drivers may encounter lane restrictions for final operations* Milling and paving operations for the 116th Street & Allisonville Road Improvement Project are now complete. Drivers should continue to expect intermittent lane restrictions as crews complete striping, traffic signal work, and restoration, including concrete work on sidewalks. Please allow extra travel time, watch for crews, and use caution through the work zone. Sidewalks within the project area remain closed while construction and concrete work continue. For the latest construction updates:
Questions? Contact the Engineering Department at drivefishers@fishersin.gov.
Southeastern Parkway & Olio Road Roundabout Improvements **MAJOR UPDATE BELOW** Construction is underway on the Southeastern Parkway and Olio Road roundabout to improve safety and traffic flow at one of the region’s busiest intersections. The fifth leg of the roundabout has permanently closed to traffic. TRAFFIC ALERT: Major Changes Coming to Olio Road & Southeastern Parkway Roundabout Phase 2 of the Olio Road & Southeastern Parkway Roundabout Reconstruction Project is ongoing. With work anticipated to continue through the end of the year During this phase, significant traffic restrictions will be in place, including the closure of the roundabout connections used to travel north and south on Olio Road. What Drivers Need to Know:
IMPORTANT: Review the Attached Detour Map Hospital Detour Maps Below: Hospital Detour Map (IU Health) All of the routes and traffic changes outlined above are illustrated on the attached Phase 2 detour map. Drivers are strongly encouraged to review the map before traveling through the area to identify the appropriate route for their destination. Depending on your direction of travel, alternate routes may include 134th Street, 136th Street, and the newly constructed roadway connection. Additional Reminders:
All construction dates are weather-dependent and subject to change. Project Details & Detour Maps: FishersIN.gov/Olio Questions? DriveFishers@fishersin.gov |
|
| Utility Work | |
| Cumberland Road Utility Work – Duke Project
Lane restrictions continue between 106th Street and 116th Street from 9 a.m. to 3 p.m.
ATT Utility Work
ATT will be installing fiber throughout the following neighborhods: Beaver Ridge, Pine Bluff Overlook, Bradford Ridge, Walnut Creek, Delaware Pointe, Summerfield, Delaware Crossing. Work will be begin in the next week and will be conducted in utility easements behind the sidewalk. Att has been working in the in the Limesprings Neighborhood.
Upcoming Brightspeed Fiber Installation
Brightspeed is expected to begin fiber installation work next week in the following neighborhoods:
Residents may notice door hangers being distributed and utility locate flags appearing in advance of construction. These are part of the preparation process before work begins.
For more information on Fiber installation and what you can expect, please visit https://fishersin.gov/services-resources/resident-resources/homeowners-associations/ |
|
| Project Updates | |
| 131st and Brooks School Road Roundabout
A new roundabout will be constructed at the intersection of 131st Street and Brooks School Road. Drivers can expect periodic lane restrictions in the current utility relocation phase.
USA Parkway Widening Project (North of 106th Street) Project Update Motorists can expect periodic lane restrictions on USA Parkway north of 106th Street as our contractor finalizes operations on the USA Parkway Widening Project. Lane restrictions continue to be in place through the end of November, weather permitting. The project is substantially complete, with final restoration and punch list work continuing into November. Please slow down, watch for construction crews, and allow extra travel time when traveling through the area. As always, schedules are weather dependent and subject to change.
Resurfacing Project Road Resurfacing Update Crews are making significant progress on the City’s 2026 resurfacing program, with work substantially complete in several neighborhoods and along major roadways. Resurfacing Package 26-1 Resurfacing is substantially complete with striping operations pending. Residents will still see crews returning to areas where resurfacing operations were conducted to complete final operations. Resurfacing Package 26-2 Crews are finalizing work in the Springs of Cambridge neighborhood. Drivers may continue to see crews completing final work in resurfaced areas. Please slow down, watch for workers and equipment, and follow posted traffic restrictions. As always, construction schedules are weather dependent and subject to change.
For additional project information, view the Capital Project Dashboard here.
|
|
| CLEARPATH IMPROVEMENT PROJECT
KNOW BEFORE YOU GO: What to Expect –Click Here Southbound I-69 now in final configuration
Upcoming Short-Term Closures Drivers can expect the following closures from 9 p.m. to 6 a.m.: Friday, Nov. 6 and Saturday, Nov. 7
October through Late November Knue Road closed at the Nickel Plate Trail crossing (beginning on or after Monday, Oct. 26) For schedule updates, follow the project on Facebook, X and Instagram, and subscribe to email and text message alerts at ClearPath465.com. Long-Term Closures Ramp from northbound Binford Boulevard to westbound I-465 closed
For more information Visit the Clearpath465 website. |
|