Drivers heading into Thanksgiving week in Fishers should plan for detours at the Southeastern Parkway and Olio Road roundabout and a brief signal outage on 116th Street, according to the city’s weekly road construction report.
Phase 2 of the Olio Road and Southeastern Parkway roundabout reconstruction is still the biggest traffic disruption in the area. Work is expected to continue through the end of the year. The roundabout connections used to travel north and south on Olio Road are closed, and the roundabout’s fifth leg has closed permanently.
Southbound Olio Road traffic is being sent west onto Campus Parkway/146th Street. Northbound drivers must detour on 136th Street and a newly built connection to Southeastern Parkway. Eastbound traffic uses a bypass lane toward IU Health Fishers, and one westbound lane stays open through the roundabout. Nearby businesses, hospitals and medical offices remain open. The city urges drivers to check the detour maps at FishersIN.gov/Olio before traveling.
Beginning at 9 a.m. Tuesday, Nov. 24, crews will replace a damaged traffic signal cabinet at the Fresh Thyme intersection on 116th Street. The intersection will run under stop control during the work, which should be finished before the evening rush hour.
Elsewhere, 136th Street between Southeastern Parkway and Prairie Baptist Road reopened Nov. 6. Intermittent lane restrictions are still possible while crews finish the widening project. The 116th Street and Allisonville Road intersection is open, but lane restrictions continue for signal and concrete work, and sidewalks in the project area remain closed.
Other work in the report:
- Utility relocation continues at 131st Street and Brooks School Road, where a new roundabout will be built. Expect periodic lane restrictions.
- Lane restrictions on USA Parkway north of 106th Street are expected through the end of November as the widening project wraps up.
- Duke utility work on Cumberland Road between 106th and 116th streets brings lane restrictions from 9 a.m. to 3 p.m.
- AT&T plans to begin fiber installation next week in Beaver Ridge, Pine Bluff Overlook, Bradford Ridge, Walnut Creek, Delaware Pointe, Summerfield and Delaware Crossing. Brightspeed is expected to start fiber work in The Boulders, Reserve at Steeplechase, Sanctuary at Steeplechase and Oakhurst.
- The city’s 2026 resurfacing program is substantially complete on 131st Street, Howe Road and Promise Road. Final pavement markers have not been installed yet.
South of Fishers, the ClearPath I-465/I-69 project has several weekend closures. The ramp from eastbound I-465 to northbound I-69 and 82nd Street closes from 9 p.m. Saturday, Nov. 21, through 5 a.m. Monday, Nov. 23. A signed detour will turn drivers around at U.S. 36. The ramp from eastbound I-465 to southbound Binford Boulevard will be closed from 9 p.m. Friday through 5 a.m. Monday. Details are at ClearPath465.com.
For updates, visit FishersIN.gov/RoadConstruction, follow @DriveFishers on X or email drivefishers@fishersin.gov.
The full report follows.
| | |
| Road Closures and Traffic Impacts – At a Glance | |
|
|
| Major Closures and Detours | |
| 136th Street Widening – Southeastern Parkway and Prairie Baptist Road
136th Street between Southeastern Parkway and Prairie Baptist Road has reopened as of Friday, November 6. Drivers may encounter intermittent lane restrictions as crews complete final work on the widening project. Please continue to use caution, follow posted signage, and stay alert for crews working in the area. Road Improvements at 116th St & Allisonville Rd *Open but drivers may encounter lane restrictions for final operations* Drivers should continue to expect intermittent lane restrictions as crews traffic signal work, and restoration, including concrete work on sidewalks. Please allow extra travel time, watch for crews, and use caution through the work zone. All barrels will be removed once ALL work is complete. Sidewalks within the project area remain closed while construction and concrete work continue. For the latest construction updates:
Questions? Contact the Engineering Department at drivefishers@fishersin.gov.
Southeastern Parkway & Olio Road Roundabout Improvements PHASE 2 Construction is underway on the Southeastern Parkway and Olio Road roundabout to improve safety and traffic flow at one of the region’s busiest intersections. The fifth leg of the roundabout has permanently closed to traffic. TRAFFIC ALERT: Major Changes Coming to Olio Road & Southeastern Parkway Roundabout Phase 2 of the Olio Road & Southeastern Parkway Roundabout Reconstruction Project is ongoing. With work anticipated to continue through the end of the year During this phase, significant traffic restrictions will be in place, including the closure of the roundabout connections used to travel north and south on Olio Road. What Drivers Need to Know:
IMPORTANT: Review the Attached Detour Map Hospital Detour Maps Below: Hospital Detour Map (IU Health) All of the routes and traffic changes outlined above are illustrated on the attached Phase 2 detour map. Drivers are strongly encouraged to review the map before traveling through the area to identify the appropriate route for their destination. Depending on your direction of travel, alternate routes may include 134th Street, 136th Street, and the newly constructed roadway connection. Additional Reminders:
All construction dates are weather-dependent and subject to change. Project Details & Detour Maps: FishersIN.gov/Olio Questions? DriveFishers@fishersin.gov |
|
| Utility Work | |
| 116th Street at Fresh Thyme | Traffic Signal Maintenance
On Tuesday, November 24, beginning at 9 a.m., crews will replace the damaged traffic signal cabinet at the Fresh Thyme intersection on 116th Street. The intersection will operate under stop control during the work, which is expected to be completed before the evening rush hour. Drivers should expect delays, use caution, and follow posted traffic controls when traveling through the intersection. Cumberland Road Utility Work – Duke Project Lane restrictions continue between 106th Street and 116th Street from 9 a.m. to 3 p.m.
ATT Utility Work
ATT will be installing fiber throughout the following neighborhods: Beaver Ridge, Pine Bluff Overlook, Bradford Ridge, Walnut Creek, Delaware Pointe, Summerfield, Delaware Crossing. Work will be begin in the next week and will be conducted in utility easements behind the sidewalk. Att has been working in the in the Limesprings Neighborhood.
Upcoming Brightspeed Fiber Installation
Brightspeed is expected to begin fiber installation work next week in the following neighborhoods:
Residents may notice door hangers being distributed and utility locate flags appearing in advance of construction. These are part of the preparation process before work begins.
For more information on Fiber installation and what you can expect, please visit https://fishersin.gov/services-resources/resident-resources/homeowners-associations/ |
|
| Project Updates | |
| 131st and Brooks School Road Roundabout
A new roundabout will be constructed at the intersection of 131st Street and Brooks School Road. Drivers can expect periodic lane restrictions in the current utility relocation phase.
USA Parkway Widening Project (North of 106th Street) Project Update Motorists can expect periodic lane restrictions on USA Parkway north of 106th Street as our contractor finalizes operations on the USA Parkway Widening Project. Lane restrictions continue to be in place through the end of November, weather permitting. The project is substantially complete, with final restoration and punch list work continuing into November. Please slow down, watch for construction crews, and allow extra travel time when traveling through the area. As always, schedules are weather dependent and subject to change.
Resurfacing Project Road Resurfacing Update SUBSTANTIALLY COMPLETE Crews are making significant progress on the City’s 2026 resurfacing program, with work substantially complete in several neighborhoods and along major roadways. Resurfacing Package 26-2 Roadway work is substantially complete on 131st Street, Howe Road, and Promise Road, with final pavement markers still to be installed. Some additional final punch list items also remain at Promise Road and 126th Street. Milling and striping operations have been completed in the Springs of Cambridge neighborhood with only some concrete work remaining. Drivers may continue to see crews completing final work in resurfaced areas. Please slow down, watch for workers and equipment, and follow posted traffic restrictions. As always, construction schedules are weather dependent and subject to change. For additional project information, view the Capital Project Dashboard here.
|
|
| CLEARPATH IMPROVEMENT PROJECT
KNOW BEFORE YOU GO: What to Expect –Click Here Southbound I-69 now in final configuration
Upcoming Short-Term Closures Friday, Nov. 20 (9 p.m. to 6 a.m.)
9 p.m. Friday, Nov. 20 through 5 a.m. Monday, Nov. 23
Saturday, Nov. 21 and Sunday, Nov. 22 (Nightly Closures — 9 p.m. to 6 a.m.)
9 p.m. Saturday, Nov. 21 through 5 a.m. Monday, Nov. 23
October through Late November Knue Road closed at the Nickel Plate Trail crossing (beginning on or after Monday, Oct. 26)
Long-Term Closures Ramp from northbound Binford Boulevard to westbound I-465 closed For schedule updates, follow the project on Facebook, X and Instagram, and subscribe to email and text message alerts at ClearPath465.com. |
|