Road Construction Intensifies Around Fishers

The list of road construction projects for the work week of Monday, June 13th, is longer than the previous list.  We are into the heart of the road construction season.  Projects include city, county and state crews.

Here is the full listing, as provided by the City of Fishers…..

=========================================================

BRIDGE REPLACEMENT

Effective Monday, June 13th, the bridge on 106th Street between Allisonville Road and Hague Road will be closed by the Hamilton County Highway Department for replacement. Detour routes will be displayed in the area and access to local traffic will be permitted for residents and businesses. Please direct any questions about this project toalison.krupski@hamiltoncounty.in.gov.

CURB REPAIRS

A contractor will be repairing curb ramps in Bluff and Links at Grey Eagle through the coming weeks. Please anticipate periodic lane restrictions in those areas.

FALL CREEK TRAIL

Fall Creek Trail reconstruction work continues; the pedestrian bridges and section of sidewalk along the trail have been removed. Pedestrians should not use the trail within the sections that have been removed. In addition, there will be periodic lane closures along the project. Please travel with caution, construction barrels have reduced the existing northbound lane width.

I-69 AND CAMPUS PARKWAY

Milestone Contractors has begun mobilizing cranes and other equipment and setting a temporary concrete barrier wall along I-69 at Campus Parkway Exit 210. Work will require alternating lane closures on northbound and southbound I-69 between 9 p.m. and 6 a.m. Lane closures may recur each night through the end of the week depending on weather and progress. Questions about this project should be directed to INDOT at eastcentralin@indot.in.gov or 1-855-463-6848.

I-69 TRAFFIC RESTRICTIONS

INDOT is overseeing an overnight closure on multiple traffic lanes on I-69 overnight this week to continue demolition of the 106th Street overpass bridge. Weather permitting, lane closures and rolling slowdowns of traffic will begin after 9 p.m. and are expected to end before 6 a.m. the next day. Construction schedules and traffic restrictions are subject to change, and questions should be directed to INDOT at indot.carsporgram.org, 1-800-261-ROAD (7623) or 511 from a mobile phone.

PAVING

A contractor will be paving streets on Lantern Road from 131st Street to Harrison Parkway, Conner Knoll and Gray Eagle throughout the coming weeks. Please anticipate periodic lane restrictions in those areas.

STATE ROAD 37

Various geotechnical work has begun along the State Road 37 corridor. Work will take place starting at the 126th Street intersection. Learn more atwww.Fishers.in.us/SR37.

96th STREET

There will be lane restrictions on eastbound 96th Street between Allisonville Road and Masters Road between the hours of 7 p.m. and 6 a.m. Work began the evening of June 6th and last until June 25th. All restrictions will take place at night, and barrels with police officers will help direct traffic.

96th STREET AND CUMBERLAND ROAD

The Hamilton County Highway Department has closed 96th Street and Cumberland Road for 100 calendar days in order to construct a roundabout at this intersection. Anyone with concerns about this project should call 773-7770. Please visit www.Fishers.in.us/DriveFishers to view a detour map. The tentative completion date for this project is June 30, 2016.

106th STREET INTERCHANGE

INDOT has begun work on the 106th Street interchange. A lane shift is currently in place on I-69 and 106th Street is closed as construction continues. Additional details about this project will be released through INDOT and shared on the weekly construction update. Please be advised the speed limit from 82nd Street to 116th Street has been reduced to 55 mph and there are lane shifts on I-69. Please travel with caution and pay close attention to signage in the area.

116th STREET

There may be short-term lane restrictions on eastbound 116th Street between USA Parkway and Exit Five Parkway while utility work is being completed.

126th STREET

  • Continuing the week of June 16th, there will be intermittent lane restrictions for westbound traffic just west of Promise Road. These restrictions will allow the contractor to construct the entrance into Granite Ridge subdivision. Advance warning signs will be in place including a directional arrow board, as needed.
  • Temporary lane restrictions will be in place on 126th Street between Cyntheanne Road and Atlantic Road in order for shoulder work to be completed. Please drive with caution in the area.

Reminder – Fishers Has a Fireworks Ordinance

With the 4th of July weekend about 3 weeks away, I am already beginning to hear some fireworks as I move around Fishers.  Local authorities remind residents that the city does have a fireworks ordinance.  Violations can lead to a fine of $150 for the first offense, $250 per violation after the first citation.  Fireworks are allowed from 10am to midnight on July 4th.  Fireworks are allowed 5pm until 2 hours after sunset, on the following dates:

June 29

June 30

July 1

July 2

July 3

July 5

July 6

July 7

July 8

July 9

 

Below you will find the full text of the Fishers ordinance governing fireworks.  (Note: you may see references to the town…attorneys with the City of Fishers say the ordinance is still in force even though Fishers has now become a city).

=======================================================================

§ 99.01 DEFINITION OF CONSUMER FIREWORK.

Bookmark§ 99.01 DEFINITION OF CONSUMER FIREWORK.

For purpose of this chapter, the following definition shall apply unless the context clearly indicates or requires a different meaning.

CONSUMER FIREWORK.

(1) A small firework that is designed primarily to produce visible effects by combustion and that is required to comply with the construction, chemical composition, and labeling regulations promulgated by the United States Consumer Product Safety Commission under 16 CFR 1507. The term also includes some small devices designed to produce an audible effect, such as whistling devices, ground devices containing 50 milligrams or less of explosive composition, and aerial devices containing 130 milligrams or less of explosive composition. Propelling or expelling charges consisting of a mixture of charcoal, sulfur, and potassium nitrate are not considered as designed to produce an audible effect. CONSUMER FIREWORK includes but may not be limited to the following:

(a) Aerial devices, which include sky rockets, missile type rockets, helicopter or aerial spinners, roman candles, mines, and shells;

(b) Ground audible devices, which include firecrackers, salutes, and chasers; and

(c) Firework devices containing combinations of the effects described in divisions (1)(a) and (b) above.

(1) The following items are specifically excluded from the definition of CONSUMER FIREWORK:

(a) Model rockets;

(b) Toy pistol caps;

(c) Emergency signal flares;

(d) Matches;

(e) Fixed ammunition for firearms;

(f) Ammunition components intended for use in firearms, muzzle loading cannons, or small arms;

(g) Shells, cartridges, and primers for use in firearms, muzzle loading cannons, or small arms;

(h) Indoor pyrotechnics special effects material; or

(i) M-80s, cherry bombs, silver salutes, and any device banned by the federal government.

(3) In addition, the following items are excluded from the definition of CONSUMER FIREWORKS but are and shall continue to be subject to applicable permitting requirements and state statutes governing fireworks:

(a) Dipped sticks or wire sparklers;

(b) Cylindrical fountains;

(c) Cone fountains;

(d) Illuminating torches;

(e) Wheels;

(f) Ground spinners;

(g) Flitter sparklers;

(h) Snakes or glow worms;

(i) Smoke devices; and

(j) Trick noisemakers, which include:

1. Party poppers;

2. Booby traps;

3. Snappers;

4. Trick matches;

5. Cigarette loads; and

6. Auto burglar alarms.

(Ord. 041513C, passed 4-15-13)

§ 99.02 USE OF CONSUMER FIREWORKS WITHIN THE TOWN.

Bookmark§ 99.02 USE OF CONSUMER FIREWORKS WITHIN THE TOWN.

It shall be unlawful to use or display or permit to be used or displayed within Fishers’ municipal boundaries any type of consumer firework on any day or time other than the following:

(A) Between the hours of 5:00 p.m. and two hours after sunset on June 29, June 30, July 1, July 2, July 3, July 5, July 6, July 7, July 8, and July 9;

(B) Between the hours of 10:00 a.m. and 12:00 midnight on July 4; and

(C) Between the hours of 10:00 a.m. on December 31 and 1:00 a.m. on January 1.

(Ord. 041513C, passed 4-15-13)

§ 99.03 SUPERVISED PUBLIC DISPLAYS.

Bookmark§ 99.03 SUPERVISED PUBLIC DISPLAYS.

This chapter shall not apply to supervised public displays of fireworks by municipalities, fair associations, amusement parks, and other organizations or groups of individuals, all of which are and shall continue to be subject to applicable permitting requirements and state statutes.

(Ord. 041513C, passed 4-15-13)

§ 99.04 ENFORCEMENT.

Bookmark§ 99.04 ENFORCEMENT.

The Fishers Department of Fire and Emergency Services and the Fishers Police Department shall be charged with enforcing the provisions of this chapter.

(Ord. 041513C, passed 4-15-13)

§ 99.99 PENALTY.

Bookmark§ 99.99 PENALTY.

Any person, firm or corporation who violates this chapter shall be subject to a fine of $150 for the first offense and $250 for each subsequent offense. A separate offense shall be deemed committed upon each day during which a violation occurs or continues.

(Ord. 041513C, passed 4-15-13)

Reminder- Indiana law restricts the use of fireworks to the following:

·         On the user’s property;

On the property of someone who has consented to the use of fireworks on their property

HSE Schools Prepare For Decisions on Classroom Space Issues

Award winning French students answer questions from the school board
Award winning French students answer questions from the school board.

 

The Hamilton Southeastern (HSE) School Board voted to bring in more portable classroom space, but Superintendent Allen Bourff told board members he will need to have a discussion on how to provide more permanent classroom space, with the additional classes and teachers coming on line after the approval of the recent tax referendum.

Bourff said he needs to have a talk with board members about “the permanent solution to our facilities at the elementary (schools).”   Bourff says he may be prepared as early as the July 13th board session to discuss this issue.  When voters approved the referendum in this year’s primary election, classrooms were added in elementary buildings with the largest class sizes.  The school system is entering into 3-year leases for portable classrooms to provide additional classroom space.

There were several other facilities issues the board handled at the Wednesday night session.

Now that the elementary schools will have assistant principals, 7 buildings will need renovation.   HSE Schools Facilities Manager Harry Delks says the plans are still preliminary and he has no cost estimate yet.

The high school College and Career Academies are not quite one year old, and Board President Karen Harmer asked about the follow-up on unfinished items.  Delks said that is in process now and he should have a report by the July 13th board meeting.  Harmer asked that Brad Skillman, representing the contractor, be present at the July 13th session.

The board approved new signs to be placed around the Fishers High School complex allowing visitors to more easily find areas such as athletic facilities and entrances.  The board did not approve the main sign at 131st Street and Promise Road, because board members want administrators to work with the architects to improve and possibly enlarge the lettering on that sign.   HSE High School is working on a new signage plan that should be before the board soon.

 

The board honored 6 students of Hamilton Southeastern High School for earning medals at the National French Contest.  They ranked nationally in the 81st annual event, according to Lisa Narug, National Director of Le Grand Concours. Senior Fernando Sancho received a gold medal in level 3A, junior Alejandra May a silver medal in level 4A, junior Phoebus Yang a bronze medal in level 4A, and sophomores Farida Daouda, Emily Williams, and Abigail Wirtz received bronze in level 3A. Hamilton Southeastern’s reports for level 2A are yet to be reported. 

Le Grand Concours is a national competition sponsored by the American Association of Teachers of French.  Students were evaluated for their written, oral and listening comprehension skills in French.   More than 85,000 students in all 50 states competed in the 2016 event.

 

Update on I-69, Exit 210

The Indiana Department of Transportation (INDOT) has provided an update on the work going on along I-69 and the construction preparations for rebuilding Exit 210 along the same interstate highway.

Patching work will continue overnight, 9pm-6am, through next week.  The new ashphalt work is to begin next week on the highway between Exit 210 and Exit 2015 (116th St.).

Residents will also see work at the Exit 210 site, where cranes and other equipment will be put into place.

For more details, see the news release below from INDOT, issued June 7th:

============================================================

 

Interstate 69 from Exit 210 to Exit 205

Milestone Contractors plans to begin tonight patching existing pavement on southbound Interstate 69 between Campus/Southeastern Parkway Exit 210 and State Road 37 Exit 205.

Milestone expects to finish patching on northbound I-69 between Exit 205 and Exit 210 this week and begin paving a new asphalt overlay on the section next week.

Patching and paving operations require alternating lane restrictions from 9 p.m. to 6 a.m. six nights a week on Monday through Saturday nights.

One lane of I-69 will remain open at all times, and two lanes will remain open during peak daytime travel times. The speed limit on I-69 through the work zone is reduced to 60 mph and further reduced to 50 mph when workers are present.

After existing pavement is resurfaced, crews will start work to rehabilitate interstate bridges. Traffic lanes between Exit 205 and Exit 210 will be shifted toward the outside shoulders to set temporary concrete barriers and begin construction of an additional travel lane in the median.

I69_MOT_Phase_II

After existing pavement is patched and resurfaced, two traffic lanes will be shifted toward the outside shoulder to allow space to build an additional lane in the median.

 

Campus/Southeastern Parkway Exit 210

Milestone is mobilizing cranes and other equipment at the Campus/Southeastern Parkway interchange, setting temporary concrete barrier along I-69, and widening the abutments and center pier for the bridge over I-69.  To see recent photos, go to this link.

Construction of the new interchange configuration is scheduled to begin after Independence Day (July 4).  The first phase will begin building the new ramps and will prepare for shifting traffic into a double-crossover diamond configuration later this summer, which is intended to improve traffic flow during widening of the bridge deck and construction of the permanent interchange improvements.

 

exit-210-phase-1_crop

The first phase of construction will begin building the new ramps and will prepare to shift traffic into a double-crossover diamond configuration through the remainder of construction

 

About the project

INDOT and the Indiana Finance Authority (IFA) have selected a $92 million proposal from Milestone Contractors and United Consulting to add a travel lane and rehabilitate 15 miles of I-69 in Hamilton and Madison counties as part of Indiana’s Major Moves 2020 program.  The project will:

  • Resurface 15 miles of existing interstate pavement;
  • Rehabilitate existing interstate bridges and drainage structures;
  • Add a third travel lane to the interstate median in each direction from State Road 37 (Exit 205) in Fishers to north of State Road 38 (Exit 214) in Pendleton;
  • Add a southbound lane to the right outside shoulder between the 116th Street entrance ramp and the future 106th Street exit ramp, which is currently under construction;
  • Reconfigure the Campus Parkway interchange (Exit 210) into a double crossover diamond design to improve traffic flow;
  • Widen the Campus Parkway bridge over I-69;
  • Rebuild and lower the State Road 13 (Exit 214) pavement under I-69;
  • Rehabilitate the Brooks School Road and Madison County Road 650W bridges over I-69

 Construction is anticipated to be complete by the end of 2017. Updates about construction schedules will be announced as work progresses.

Fishers Census – It’s Real

This is an era when we are all automatically suspicious of nearly everything in life.  Scams, in person and online, can cost you a great deal.  Sometimes, you can even become a crime victim.  So, being careful is the normal procedure these days.

However, people in Fishers need to know there actually is a census going on.  There are census workers out in the neighborhoods working on the census count.  City government officials are encouraging local residents to cooperate with the census.

The city is paying for this special census.  Normally, a national census happens once every 10 years, with the next one set for the year 2020.  But Fishers has been growing by leaps and bounds in recent years.  The 2010 census listed the Fishers population as 83, 891. Based on estimates by city officials, that figure is creeping up closer to 90,000.

The official population count from the census is very important.  It dictates what share of state and federal money the city receives. The higher the population based on the official census, the more state and federal money will fill our city coffers.  That benefits everyone in Fishers.  The cost to the city paying for this census will be paid back many times over in additional funds from other sources, based in the higher population count.

Be clear about one thing – all of Fishers is not being counted in this census.  The city is paying the feds to verify the population count only in the growing areas of the city.  That lowered the overall cost to the city.

Eric Moeller, City Councilor and Chair of the City Council Finance Committee, posted on Facebook concerns he is receiving from constituents about the census.  Yes, the census is legitimate. You can ask for the census workers ID.  If you are suspicious you can call the Fishers Police.  But be aware there are census workers fanning out in the population growth areas of Fishers.  It is in your interest, and your fellow city dwellers interest, to cooperate with the census.  It is real.

If you want more details on the special census being conducted in parts of Fishers, use this link.

Fishers Police Department Teen Academy Coming Up Soon

 

image001

 

If you have a teen looking for something to do this month in Fishers, the local police department has an idea for you.   June 20th-25th will feature the Fishers Police Department Teen Academy.  It’s a chance for local teens to learn more about law enforcement and get acquainted with police officers.

Below is the Fishers Police Department news release with all the details..

===========================================

The 15th annual Fishers Police Department Teen Academy will be held June 20th – 24thin conjunction with the Fishers YMCA.  This year’s academy will be held at Riverside Intermediate in Fishers.  The academy is one week of law enforcement type training that will allow teens to better understand how law enforcement works.  The academy will also allow teens to get to know several officers through a variety of social activities. 
 
Each day will begin at 9:00am. The teens will start each day with physical exercise.  The students will then attend classroom training followed by practical hands on skills to reinforce the lesson of the day. Each day will conclude with a social activity between officers and students. Parents can pick up their teen at 3:30pm.
 
“The children in our community are very important to us and with the success of Teen Academy, we are excited to work with the kids again this year.” – Chief George Kehl. 
 
            The purpose of the academy is to allow teens to better understand police officers and to strengthen the relationship between the police department and the community.  Officers will teach blocks of instruction on various topics such as making traffic stops, meeting our K-9 units and learning how they work with police, learning about the Fishers Dive Team, meeting our Crime Scene Investigators, learning about Internet Safety and much more. Students will have classroom instruction as well as practical “role play” training each day.
 
            The academy is open to any applicant 13 years of age or older.  Applicants must be enrolled in a junior high or high school in Fishers.  Each applicant is subject to a screening process and therefore walk-ins will not be allowed. We only have 40 spots available for this year’s academy!  If you are interested, please contact Officer Cory Robinson at robinsonc@fishers.in.us to begin the screening process. 

A Few Thoughts on Muhammed Ali

 

Aliimages

 

When I learned of the passing of Muhammad Ali, I starting watching, listening and reading the tributes to the late heavyweight boxing champ, who became much more than a sports figure in America.  But the Muhammad Ali being discussed today was not the celebrity I read about in the 1960s.

First, no one gave the man then called Cassius Clay any chance of beating Sonny Liston in their first heavyweight championship match in Miami Beach held on February 25th, 1964. That included all the newspaper writers regularly covering the boxing beat (there were many in those days).  It also included all the so-called boxing “experts” of that era.

I don’t blame any of them for predicting a dominating Liston win.  There were major contenders for the title that refused to even box Liston….he was known as a powerful boxer with an even more powerful punch.  In the heavyweight division, a boxer like Liston could dominate.

But Clay (as he was known at the time) did something boxing orthodoxy of the time said not to do.  He used his speed and quickness in the ring to wear out his opponent.  The match went 6 rounds, with Liston not coming out for round 7.  Ali was the Heavyweight Boxing Champion of the World.

The day after the fight, Clay announced he was joining the Nation of Islam.  He later changed his name to Muhammad Ali.

There was a rematch scheduled between Liston and Ali, but Ali had emergency hernia surgery that delayed the bout.  Boston Gardens was the original site for the rematch, but for a number of reasons, Boston backed out.  At the last minute the small town of Lewiston, Maine, population 41,000, became the new site of the rematch set for May 25th, 1965.  Only 2,434 boxing fans showed up in a venue that could handle a crowd of 4,900. There were many security concerns.  The FBI took many of the threats of violence seriously enough that law enforcement posted a 12-man, 24-hour guard around Ali before and during the fight.

In one of the shortest heavyweight title fights in boxing history, Ali won again when Listen fell to the ring canvas abut one minute into the first round.  There was mass confusion after that, but the officials ruled Listen was down for the count.

Those 2 fights were controversial, but Ali won both.

Muhammad Ali was not able to box during years of his prime because he refused to be inducted into the military.  Many people today were born long after the military draft was abolished, but at one time, it was considered your patriotic responsibility to report for duty if drafted.  Ali opposed the Vietnam War and said he refused to serve on religious grounds. Boxing regulators stripped him of his title and his ability to fight as a boxer professionally. Eventually, the United States Supreme Court ruled in Ali’s favor and he avoided prison.  With the legal troubles settled, Ali was allowed to get back into the ring.

What most people don’t realize is just how hated Ali was by many people during most of the 1960s.  The Vietnam War was not always unpopular with Americans as a whole, particularly in the early years of the conflict.  Many hated Ali not just for his stance on the war, but for his association with the Nation of Islam.  To put it bluntly, Muhammad Ali scared a lot of white Americans in the 1960s.

Then his reputation began to slowly change during the 1970s and into the 1980s.  Ali had contracted Parkinson’s Disease, but remained active, particularly in supporting causes of peace and charitable work.  Many say Muhammad Ali was the most popular man in earth, with the best-known countenance in the world.

I thought about all this when watching, reading and listening to all the praises being expressed at the death of Muhammad Ali.  He was a polarizing figure early in his life, then became something else entirely in the later years of his life – a highly respected man.

Muhammad Ali may well have been the best athlete of the 20th Century.  He knew how to promote himself (whether you liked it or not).  Those 2 things would be enough to cement a legacy.  But Muhammad Ali was more than that.  He was a cultural icon known throughout the world.  That’s how most of us will remember him.

Long List of Road Construction, Work Week Starting Monday, June 6th

As street and road work continues in and around the city of Fishers, the list is too long to summarize.  Work continues on the 106th Street I-69 interchange, and preparation work continues for the redesign of Exit 210 on I-69 (near Saxony).  Here’s the full list below, as provided by the City of Fishers:

==============================================

BRIDGE REPLACEMENT

Effective Monday, June 13th, the bridge on 106th Street between Allisonville Road and Hague Road will be closed by the Hamilton County Highway Department for replacement. Detour routes will be displayed in the area and access to local traffic will be permitted for residents and businesses. Please direct any questions about this project toalison.krupski@hamiltoncounty.in.gov.

CURB REPAIRS

A contractor will be repairing curb ramps in Bluff and Links at Grey Eagle through the coming weeks. Please anticipate periodic lane restrictions in those areas.

FALL CREEK TRAIL

Fall Creek Trail reconstruction work continues; the pedestrian bridges and section of sidewalk along the trail have been removed. Pedestrians should not use the trail within the sections that have been removed. In addition, there will be periodic lane closures along the project throughout the week of May 30th. Please travel with caution, construction barrels have reduced the existing northbound lane width.

I-69 AND CAMPUS PARKWAY

Milestone Contractors has begun mobilizing cranes and other equipment and setting a temporary concrete barrier wall along I-69 at Campus Parkway Exit 210. Work will require alternating lane closures on northbound and southbound I-69 between 9 p.m. and 6 a.m. Lane closures may recur each night through the end of the week depending on weather and progress. Questions about this project should be directed to INDOT at eastcentralin@indot.in.gov or 1-855-463-6848.

I-69 TRAFFIC RESTRICTIONS

INDOT is overseeing an overnight closure on multiple traffic lanes on I-69 overnight this week to continue demolition of the 106th Street overpass bridge. Weather permitting, lane closures and rolling slowdowns of traffic will begin after 9 p.m. and are expected to end before 6 a.m. the next day. Construction schedules and traffic restrictions are subject to change, and questions should be directed to INDOT at indot.carsporgram.org, 1-800-261-ROAD (7623) or 511 from a mobile phone.

PAVING

A contractor will be paving streets on Lantern Road from 131st Street to Harrison Parkway, Conner Knoll and Gray Eagle throughout the coming weeks. Please anticipate periodic lane restrictions in those areas.

STATE ROAD 37
Continued work will take place along the State Road 37 corridor this weekend from June 3rd through 6th. Work will include archeological and historic reconnaissance from 126th Street in Fishers to State Road 32 in Noblesville. Learn more at www.Fishers.in.us/SR37.

96th STREET

There will be lane restrictions on eastbound 96th Street between Allisonville Road and Masters Road between the hours of 7 p.m. and 6 a.m. Work will start on the evening of June 6th and last until June 25th. All restrictions will take place at night, and barrels with police officers will help direct traffic.

96th STREET AND CUMBERLAND ROAD

The Hamilton County Highway Department has closed 96th Street and Cumberland Road for 100 calendar days in order to construct a roundabout at this intersection. Anyone with concerns about this project should call 773-7770. Please visit www.Fishers.in.us/DriveFishers to view a detour map. The tentative completion date for this project is June 30, 2016.

106th STREET INTERCHANGE

INDOT has begun work on the 106th Street interchange. A lane shift is currently in place on I-69 and 106th Street is closed as construction continues. Additional details about this project will be released through INDOT and shared on the weekly construction update. Please be advised the speed limit from 82nd Street to 116th Street has been reduced to 55 mph and there are lane shifts on I-69. Please travel with caution and pay close attention to signage in the area.

116th STREET

There may be short-term lane restrictions on eastbound 116th Street between USA Parkway and Exit Five Parkway while utility work is being completed.

126th STREET

  • Continuing the week of May 30th, there will be intermittent lane restrictions for westbound traffic just west of Promise Road. These restrictions will allow the contractor to construct the entrance into Granite Ridge subdivision. Advance warning signs will be in place including a directional arrow board, as needed.

  • Temporary lane restrictions will be in place on 126th Street between Cyntheanne Road and Atlantic Road in order for should work to be completed. Please drive with caution in the area.

106th Street East of Allisonville Closing 90 Days For Bridge Replacement

The Hamilton County Highway Department announced Friday afternoon that 106th Street in Fishers will be closed just east of Allisonville Road for 90 days in order to replace the bridge over Cheney Creek.  County governments in Indiana are normally responsible for the construction and maintenance of bridges.

Below is part of the news release issued by the county highway department:

==============================================

Effective Monday, June 13, 2016, E. 106th Street between Allisonville Road and Hague Road will be closed for the replacement of Bridge #261, E.106th Street over Cheeney Creek. Currently, E. 106th Street is closed and will continue to be closed to through traffic from Lantern Road/Crosspoint Boulevard to Lantern Road/USA Parkway for the new 106th Street interchange project with the Indiana Department of Transportation.

East 106th Street between Allisonville Road and Hague Road is scheduled to be closed for 90 days.

The signed detour will consist of Allisonville Road, 116th Street, and Hague Road. All through traffic is advised to follow the signed detour or find an alternate route. During the road closure, access will be provided to local traffic from the east (Hague Road) for residences and businesses. Access from the west (Allisonville Road) to Metro Storage and Anthony Builders will be available.